1998 Minnesota Statutes
- Search Minnesota Statutes
- About Minnesota Statutes
- 1998 Statutes New, Amended or Repealed
- 1998 Table of Chapters
Chapter 216B
Section 216B.2424
Recent History
- 2023 Subd. 5c Amended 2023 c 60 art 9 s 8
- 2021 Subd. 5b New 2021 c 23 s 1
- 2021 Subd. 5c New 2021 c 23 s 2
- 2017 Subd. 9 New 2017 c 94 art 10 s 20
- 2016 Subd. 5a Amended 2016 c 157 s 1
- 2013 Subd. 5a Amended 2013 c 57 s 1
- 2009 Subd. 5a Amended 2009 c 110 s 22
- 2008 Subd. 1 Amended 2008 c 296 art 1 s 12
- 2006 Subd. 5 Amended 2006 c 259 art 4 s 4
- 2005 Subd. 1 Amended 2005 c 97 art 5 s 1
- 2005 Subd. 1a Amended 2005 c 1 art 2 s 140
- 2005 Subd. 1a New 2005 c 97 art 5 s 2
- 2005 Subd. 2 Amended 2005 c 97 art 5 s 3
- 2005 Subd. 5a Amended 2005 c 97 art 5 s 4
- 2005 Subd. 6 Amended 2005 c 97 art 5 s 5
- 2005 Subd. 8 Amended 2005 c 97 art 5 s 6
- 2003 Subd. 5 Amended 2003 c 11 art 2 s 7
- 2003 Subd. 5 Amended 2003 c 127 art 2 s 3
- 2003 Subd. 5a New 2003 c 11 art 2 s 16
- 2002 Subd. 5 Amended 2002 c 379 art 1 s 55
- 2001 Subd. 5 Amended 2001 c 5 art 3 s 13
- 2001 Subd. 6 Amended 2001 c 7 s 46
- 2000 Subd. 3 Amended 2000 c 443 s 1
- 2000 Subd. 5 Amended 2000 c 443 s 2
- 2000 Subd. 6 New 2000 c 443 s 3
- 2000 Subd. 7 New 2000 c 443 s 4
- 2000 Subd. 8 New 2000 c 443 s 5
- 1998 Subd. 3 Amended 1998 c 345 s 2
- 1996 216B.2424 Amended 1996 c 450 s 1
- 1995 216B.2424 Amended 1995 c 224 s 76
- 1994 216B.2424 New 1994 c 641 art 3 s 3
216B.2424 Biomass power mandate.
Subdivision 1. Farm-grown closed-loop biomass. For the purposes of this section, "farm-grown closed-loop biomass" means biomass, as defined in section 216C.051, subdivision 7, that:
(1) is intentionally cultivated, harvested, and prepared for use, in whole or in part, as a fuel for the generation of electricity;
(2) when combusted, releases an amount of carbon dioxide that is less than or approximately equal to the carbon dioxide absorbed by the biomass fuel during its growing cycle; and
(3) is fired in a new or substantially retrofitted electric generating facility that is:
(i) located within 400 miles of the site of the biomass production; and
(ii) designed to use biomass to meet at least 75 percent of its fuel requirements.
The legislature finds that the negative environmental impacts within 400 miles of the facility resulting from transporting and combusting the biomass are offset in that region by the environmental benefits to air, soil, and water of the biomass production.
Among the biomass fuel sources that meet the requirements of clause (2) are poplar, aspen, willow, switch grass, sorghum, alfalfa, and cultivated prairie grass.
Subd. 2. Interim exemption. (a) A biomass project proposing to use, as its primary fuel over the life of the project, short rotation woody crops, may use as an interim fuel agricultural waste and other biomass which is not farm-grown closed-loop biomass for up to six years after the project's electric generating facility becomes operational; provided, the project developer demonstrates the project will use the designated short rotation woody crops as its primary fuel after the interim period and provided the location of the interim fuel production meets the requirements of subdivision 1, clause (3).
(b) A biomass project proposing to use, as its primary fuel over the life of the project, short rotation woody crops, may use as an interim fuel agricultural waste and other biomass which is not farm-grown closed-loop biomass for up to three years after the project's electric generating facility becomes operational; provided, the project developer demonstrates the project will use the designated short rotation woody crops as its primary fuel after the interim period.
(c) A biomass project that uses an interim fuel under the terms of paragraph (b) may, in addition, use an interim fuel under the terms of paragraph (a) for six years less the number of years that an interim fuel was used under paragraph (b).
(d) A project developer proposing to use an exempt interim fuel under paragraphs (a) and (b) must demonstrate to the public utility that the project will have an adequate supply of short rotation woody crops which meet the requirements of subdivision 1 to fuel the project after the interim period.
Subd. 3. Fuel exemption. Over the duration of the contract of a biomass power facility selected to satisfy the mandate in subdivision 5, fuel sources that are not biomass may be used to satisfy up to 25 percent of the fuel requirements of a biomass power facility selected to satisfy the biomass power mandate in subdivision 5. A biomass power facility selected to satisfy the mandate in subdivision 5 also may use fuel sources that are not biomass during any period when biomass fuel sources are not reasonably available to the facility due to any circumstances constituting an act of God. Fuel sources that are not biomass used during such a period of biomass fuel source unavailability shall not be counted toward the 25 percent exemption provided in this subdivision. For purposes of this subdivision, "act of God" means any natural disaster or other natural phenomenon of an exceptional, inevitable, or irresistible character, including, but not limited to, flood, fire, drought, earthquake, and crop failure resulting from climatic conditions, infestation, or disease.
Subd. 4. Financial viability. A biomass project developer must demonstrate to the public utility evidence of sufficient financial viability necessary for the construction and operation of the biomass project.
Subd. 5. Mandate. A public utility, as defined in section 216B.02, subdivision 4, that operates a nuclear-powered electric generating plant within this state must construct and operate, purchase, or contract to construct and operate (1) by December 31, 1998, 50 megawatts of electric energy installed capacity generated by farm-grown closed-loop biomass scheduled to be operational by December 31, 2001; and (2) by December 31, 1998, an additional 75 megawatts of installed capacity so generated scheduled to be operational by December 31, 2002. Of the total 125 megawatts of biomass electric energy installed capacity required under this section, no more than 75 megawatts may be provided by a single project. Of the 75 megawatts of biomass electric energy installed capacity required under clause (2), no more than 25 megawatts of this capacity may be provided by a St. Paul district heating and cooling system cogeneration facility utilizing waste wood as a primary fuel source. The St. Paul district heating and cooling system cogeneration facility need not use biomass that complies with the definition in subdivision 1. The public utility must accept and consider on an equal basis with other proposals a proposal to satisfy the requirements of this section that includes a project that exceeds the megawatt capacity requirements of either clause (1) or (2) and that proposes to sell the excess capacity to the public utility or to other purchasers.
HIST: 1994 c 641 art 3 s 3; 1995 c 224 s 76; 1996 c 450 s 1; 1998 c 345 s 2
Official Publication of the State of Minnesota
Revisor of Statutes