216B.2424 Biomass power mandate.
Subdivision 1. Farm-grown closed-loop biomass. (a) For the purposes of this section, "farm-grown closed-loop biomass" means biomass, as defined in section 216C.051, subdivision 7, that:
(1) is intentionally cultivated, harvested, and prepared for use, in whole or in part, as a fuel for the generation of electricity;
(2) when combusted, releases an amount of carbon dioxide that is less than or approximately equal to the carbon dioxide absorbed by the biomass fuel during its growing cycle; and
(3) is fired in a new or substantially retrofitted electric generating facility that is:
(i) located within 400 miles of the site of the biomass production; and
(ii) designed to use biomass to meet at least 75 percent of its fuel requirements.
(b) The legislature finds that the negative environmental impacts within 400 miles of the facility resulting from transporting and combusting the biomass are offset in that region by the environmental benefits to air, soil, and water of the biomass production.
(c) Among the biomass fuel sources that meet the requirements of clause (2) are poplar, aspen, willow, switch grass, sorghum, alfalfa, and cultivated prairie grass.
Subd. 2. Interim exemption. (a) A biomass project proposing to use, as its primary fuel over the life of the project, short rotation woody crops, may use as an interim fuel agricultural waste and other biomass which is not farm-grown closed-loop biomass for up to six years after the project's electric generating facility becomes operational; provided, the project developer demonstrates the project will use the designated short rotation woody crops as its primary fuel after the interim period and provided the location of the interim fuel production meets the requirements of subdivision 1, clause (3).
(b) A biomass project proposing to use, as its primary fuel over the life of the project, short rotation woody crops, may use as an interim fuel agricultural waste and other biomass which is not farm-grown closed-loop biomass for up to three years after the project's electric generating facility becomes operational; provided, the project developer demonstrates the project will use the designated short rotation woody crops as its primary fuel after the interim period.
(c) A biomass project that uses an interim fuel under the terms of paragraph (b) may, in addition, use an interim fuel under the terms of paragraph (a) for six years less the number of years that an interim fuel was used under paragraph (b).
(d) A project developer proposing to use an exempt interim fuel under paragraphs (a) and (b) must demonstrate to the public utility that the project will have an adequate supply of short rotation woody crops which meet the requirements of subdivision 1 to fuel the project after the interim period.
Subd. 3. Fuel exemption. Over the duration of the contract of a biomass power facility selected to satisfy the mandate in subdivision 5, fuel sources that are not biomass may be used to satisfy up to 25 percent of the fuel requirements of a biomass power facility selected to satisfy the biomass power mandate in subdivision 5, except that agricultural crop wastes, such as oat hulls, may be used to satisfy more than 25 percent of the fuel requirements of a power facility selected to satisfy the biomass power mandate in subdivision 5 if the wastes are co-fired with the fuel authorized for the facility. A biomass power facility selected to satisfy the mandate in subdivision 5 also may use fuel sources that are not biomass during any period when biomass fuel sources are not reasonably available to the facility due to any circumstances constituting an act of God. Fuel sources that are not biomass used during such a period of biomass fuel source unavailability shall not be counted toward the 25 percent exemption provided in this subdivision. For purposes of this subdivision, "act of God" means any natural disaster or other natural phenomenon of an exceptional, inevitable, or irresistible character, including, but not limited to, flood, fire, drought, earthquake, and crop failure resulting from climatic conditions, infestation, or disease.
Subd. 4. Financial viability. A biomass project developer must demonstrate to the public utility evidence of sufficient financial viability necessary for the construction and operation of the biomass project.
Subd. 5. Mandate. (a) A public utility, as defined in section 216B.02, subdivision 4, that operates a nuclear-powered electric generating plant within this state must construct and operate, purchase, or contract to construct and operate (1) by December 31, 1998, 50 megawatts of electric energy installed capacity generated by farm-grown closed-loop biomass scheduled to be operational by December 31, 2001; and (2) by December 31, 1998, an additional 75 megawatts of installed capacity so generated scheduled to be operational by December 31, 2002.
(b) Of the 125 megawatts of biomass electricity installed capacity required under this subdivision, no more than 50 megawatts of this capacity may be provided by a facility that uses poultry litter as its primary fuel source and any such facility: (1) need not use biomass that complies with the definition in subdivision 1; (2) must enter into a contract with the public utility for such capacity, that has an average purchase price per megawatt hour over the life of the contract that is equal to or less than the average purchase price per megawatt hour over the life of the contract in contracts approved by the public utilities commission before April 1, 2000, to satisfy the mandate of this section, and file that contract with the public utilities commission prior to September 1, 2000; and (3) such capacity must be scheduled to be operational by December 31, 2002.
(c) Of the total 125 megawatts of biomass electric energy installed capacity required under this section, no more than 75 megawatts may be provided by a single project.
(d) Of the 75 megawatts of biomass electric energy installed capacity required under paragraph (a), clause (2), no more than 25 megawatts of this capacity may be provided by a St. Paul district heating and cooling system cogeneration facility utilizing waste wood as a primary fuel source. The St. Paul district heating and cooling system cogeneration facility need not use biomass that complies with the definition in subdivision 1. The public utility must accept and consider on an equal basis with other proposals a proposal to satisfy the requirements of this section that includes a project that exceeds the megawatt capacity requirements of either paragraph (a), clause (1) or (2), and that proposes to sell the excess capacity to the public utility or to other purchasers.
(e) If a public utility files a contract with the commission for electric energy installed capacity that uses poultry litter as its primary fuel source, the commission must do a preliminary review of the contract to determine if it meets the purchase price criteria provided in paragraph (b), clause (2), of this subdivision. The commission shall perform its review and advise the parties of its determination within 30 days of filing of such a contract by a public utility. A public utility may submit by September 1, 2000, a revised contract to address the commission's preliminary determination.
(f) The commission shall finally approve, modify, or disapprove no later than July 1, 2001, all contracts submitted by a public utility as of September 1, 2000, to meet the mandate set forth in this subdivision.
(g) If a public utility subject to this section exercises an option to increase the generating capacity of a project in a contract approved by the commission prior to April 25, 2000, to satisfy the mandate in this subdivision, the public utility must notify the commission by September 1, 2000, that it has exercised the option and include in the notice the amount of additional megawatts to be generated under the option exercised. Any review by the commission of the project after exercise of such an option shall be based on the same criteria used to review the existing contract.
Subd. 6. Remaining megawatt compliance process. (a) If there remain megawatts of biomass power generating capacity to fulfill the mandate in subdivision 5 after the commission has taken final action on all contracts filed by September 1, 2000, by a public utility, this subdivision governs final compliance with the biomass energy mandate in subdivision 5 subject to the requirements of subdivision 7.
(b) To the extent not inconsistent with this subdivision, the provisions of subdivisions 2, 3, 4, and 5 apply to proposals subject to this subdivision.
(c) A public utility must submit proposals to the commission to complete the biomass mandate. The commission shall require a public utility subject to this section to issue a request for competitive proposals for projects for electric generation utilizing biomass as defined in paragraph (f) of this subdivision to provide the remaining megawatts of the mandate. The commission shall set an expedited schedule for submission of proposals to the utility, selection by the utility of proposals or projects, negotiation of contracts, and review by the commission of the contracts or projects submitted by the utility to the commission.
(d) Notwithstanding the provisions of subdivisions 1 to 5 but subject to the provisions of subdivision 7, a new or existing facility proposed under this subdivision that is fueled either by biomass or by co-firing biomass with nonbiomass may satisfy the mandate in this section. Such a facility need not use biomass that complies with the definition in subdivision 1 if it uses biomass as defined in paragraph (f) of this subdivision. Generating capacity produced by co-firing of biomass that is operational as of April 25, 2000, does not meet the requirements of the mandate, except that additional co-firing capacity added at an existing facility after April 25, 2000, may be used to satisfy this mandate. Only the number of megawatts of capacity at a facility which co-fires biomass that are directly attributable to the biomass and that become operational after April 25, 2000, count toward meeting the biomass mandate in this section.
(e) Nothing in this subdivision precludes a facility proposed and approved under this subdivision from using fuel sources that are not biomass in compliance with subdivision 3.
(f) Notwithstanding the provisions of subdivision 1, for proposals subject to this subdivision, "biomass" includes farm-grown closed-loop biomass; agricultural wastes, including animal, poultry, and plant wastes; and waste wood, including chipped wood, bark, brush, residue wood, and sawdust.
(g) Nothing in this subdivision affects in any way contracts entered into as of April 25, 2000, to satisfy the mandate in subdivision 5.
(h) Nothing in this subdivision requires a public utility to retrofit its own power plants for the purpose of co-firing biomass fuel, nor is a utility prohibited from retrofitting its own power plants for the purpose of co-firing biomass fuel to meet the requirements of this subdivision.
Subd. 7. Effect on existing projects. The commission may not approve a project proposed after April 25, 2000, which would have an adverse impact on the ability of a project approved before April 25, 2000, to obtain an adequate supply of the fuel source designated for the project.
Subd. 8. Agricultural biomass requirement. Of the 125 megawatts mandated in subdivision 5, at least 75 megawatts of the generating capacity must be generated by facilities that use agricultural biomass as the principal fuel source. For purposes of this subdivision, agricultural biomass includes only farm-grown closed-loop biomass and agricultural waste, including animal, poultry, and plant wastes. For purposes of this subdivision, "principal fuel source" means a fuel source that satisfies at least 75 percent of the fuel requirements of an electric power generating facility. Nothing in this subdivision is intended to expand the fuel source requirements of subdivision 5.
HIST: 1994 c 641 art 3 s 3; 1995 c 224 s 76; 1996 c 450 s 1; 1998 c 345 s 2; 2000 c 443 s 1-5
Official Publication of the State of Minnesota
Revisor of Statutes