115.445 NOTIFICATION REQUIREMENTS.
Before the Pollution Control Agency may issue a permit for a new wastewater treatment
system that requires a national pollutant discharge elimination system permit or a state disposal
system permit, and before construction of the system may begin, the following requirements
must be met:
(1) the project proposer must provide notice to other political subdivisions as required by
section
116.182, subdivision 3a, unless section
116.182, subdivision 3a, does not apply to the
project; and
(2) the agency shall evaluate wastewater treatment alternatives to the proposed project that
are included in the facilities plan, and any comments received on the facilities plan, considering
environmental and cost factors, and shall make the information available to the public and may
make written findings regarding its evaluation.
History: 2000 c 492 art 1 s 42