This part applies to the construction of vertical heat exchangers.
A vertical heat exchanger must not be constructed, or have piping installed or removed below the frost line, until a permit has been issued by the commissioner to the well contractor or limited well/boring contractor licensed to construct vertical heat exchangers.
The well contractor or vertical heat exchanger contractor must submit to the commissioner a vertical heat exchanger permit application on a form provided by the commissioner. The application must be legible and signed by the well contractor or vertical heat exchanger contractor and the property owner or property owner's agent.
A permit application must be completed for each vertical heat exchanger and must include:
the name and address of the owner of the property on which the vertical heat exchanger will be installed;
the township number, range number, section and one quartile, and the property street address if assigned, of the proposed vertical heat exchanger;
a plan diagram showing the location of the vertical heat exchanger borings, property lines, and structures on the property;
the number, diameter, and depth of all bore holes drilled to install the vertical heat exchanger piping;
The vertical heat exchanger must be constructed within 18 months of the date the permit is issued.
MS s 103I.101; 103I.111; 103I.205; 103I.221; 103I.301; 103I.401; 103I.451; 103I.501; 103I.525; 103I.531; 103I.535; 103I.541; 103I.621; 144.05; 144.12; 144.122; 144.383; 157.04; 157.08; 157.09; 157.13
17 SR 2773; 18 SR 1222; 25 SR 1207; 33 SR 211
September 2, 2008
Official Publication of the State of Minnesota