383B.1584 DESIGN-BUILD AWARD.
The county board, after considering the recommendations of the design-build selection
panel, shall award the design-build contract to the proposer with the highest scored proposal
based on the evaluation criteria in the RFP. The rationale for the selection of the proposal must be
stated at the time of the contract award. The county board may reject any or all proposals, but
must not do so to evade the other provisions and policies of this section. If the county board
rejects all proposals, it may then solicit new proposals after making appropriate modifications
to performance criteria, budget constraints, or qualifications.
History: 2002 c 393 s 61; 2007 c 70 s 6
NOTE: See section
383B.1586 for expiration date.