Skip to main content Skip to office menu Skip to footer
Capital IconMinnesota Legislature

Office of the Revisor of Statutes

116.85 MONITORS REQUIRED FOR OTHER INCINERATORS.
    Subdivision 1. Emission monitors. Notwithstanding any other law to the contrary, an
incinerator permit that contains emission limits for dioxin, cadmium, chromium, lead, or mercury
must, as a condition of the permit, require the installation of an air emission monitoring system
approved by the commissioner. The monitoring system must provide continuous measurements to
ensure optimum combustion efficiency for the purpose of ensuring optimum dioxin destruction.
The system shall also be capable of providing a permanent record of monitored emissions that
will be available upon request to the commissioner and the general public. The commissioner
shall provide periodic inspection of the monitoring system to determine its continued accuracy.
    Subd. 1a. Mercury testing. (a) Notwithstanding any other law to the contrary, a facility
holding an incinerator permit that contains emission limits for mercury must, as a condition of
the permit, conduct periodic stack testing for mercury as described by this subdivision. Hospital
waste incinerators having a design capacity of less than 3,000,000 BTU's per hour may use
mercury segregation practices as an alternative to stack testing if allowed by applicable federal
requirements, with the approval of the commissioner.
(b) A facility shall conduct stack testing for mercury at intervals not to exceed three months.
An incinerator facility burning greater than 30 percent by weight of refuse-derived fuel must
conduct periodic stack testing for mercury at intervals not to exceed 12 months unless a previous
test showed a permit exceedence after which the agency may require quarterly testing until permit
requirements are satisfied. With the approval of the commissioner, an incinerator facility may use
methods other than stack testing for determining mercury in air emissions.
(c) After demonstrating that mercury emissions have been below 50 percent of the facility's
permitted mercury limit for three consecutive years, as tested under the conditions of paragraph
(b), an incinerator facility may choose to conduct stack testing once every three years or according
to applicable federal requirements, whichever is more stringent. The facility shall notify the
commissioner of its alternative mercury testing schedule, and the commissioner shall include
operating conditions in the facility's permit that ensure that the facility will continue to emit
mercury emissions less than 50 percent of the applicable standard.
(d) If a test conducted under the provisions of paragraph (c) shows mercury emissions
greater than 50 percent of the facility's permitted mercury limit, the facility shall conduct annual
mercury stack sampling until emissions are below 50 percent of the facility's permitted mercury
limit. Once the facility demonstrates that mercury emissions are again below 50 percent of the
facility's permitted mercury limit, the facility may resume testing every three years or according
to federal requirements, whichever is more stringent, upon notifying the commissioner.
(e) In amending, modifying, or reissuing a facility's air emissions permit which contains a
provision that restricts mercury emissions from the facility the commissioner shall, at a minimum,
continue that permit restriction at the same level unless the applicant demonstrates that no good
cause exists to do so.
    Subd. 2. Continuously monitored emissions. Should, at any time after normal startup, the
permitted facility's continuously monitored emissions exceed permit requirements, based on
accurate and valid emissions data, the facility shall immediately report the exceedance to the
commissioner and immediately either commence appropriate modifications to the facility to
ensure its ability to meet permitted requirements or commence shutdown if the modifications
cannot be completed within 72 hours. Compliance with permit requirements must then be
demonstrated based on additional testing.
    Subd. 3. Periodically tested emissions. Should, at any time after normal startup, the
permitted facility's periodically tested emissions exceed permit requirements based on accurate
and valid emissions data, the facility shall immediately report the exceedance to the commissioner,
shall undertake appropriate steps to ensure the facility's compliance with permitted requirements,
and shall demonstrate compliance within 60 days of the initial report of the exceedance. If the
commissioner determines that compliance has not been achieved within 60 days, then the facility
shall shut down until compliance with permit requirements is demonstrated based on additional
testing.
    Subd. 4. Other law. This section shall not be construed to limit the authority of the agency to
regulate incinerator operations under any other law.
History: 1989 c 335 art 1 s 133; 1990 c 594 art 1 s 54; 1997 c 189 s 1; 1999 c 235 s 2

Official Publication of the State of Minnesota
Revisor of Statutes