Skip to main content Skip to office menu Skip to footer
Capital IconMinnesota Legislature

Office of the Revisor of Statutes

216H.06 EMISSIONS CONSIDERATION IN RESOURCE PLANNING.

By January 1, 2008, the Public Utilities Commission shall establish an estimate of the likely range of costs of future carbon dioxide regulation on electricity generation. The estimate, which may be made in a commission order, must be used in all electricity generation resource acquisition proceedings. The estimates, and annual updates, must be made following informal proceedings conducted by the commissioners of commerce and pollution control that allow interested parties to submit comments.

Official Publication of the State of Minnesota
Revisor of Statutes