177.435 FACILITY CONSTRUCTION; PREVAILING WAGE.
Construction of value-added agricultural product processing facility financed in whole or in
part with a loan or grant provided under section
41A.035,
41B.044, or
41B.046 is a "project" as
that term is defined in section
177.42, subdivision 2. Contracts for the construction or expansion
of a value-added agricultural product processing facility that is a project under this section must
comply with section
177.43 if the loan or grant agreement was entered into on or after December
31, 1995.
History: 1995 c 220 s 113