16C.144 Guaranteed savings contracts.

Subdivision 1. Definitions. The following definitions apply to this section.

(a) "Utility" means electricity, natural gas, or other energy resource, water, and wastewater.

(b) "Utility cost savings" means the difference between the utility costs under the precontract conditions and the utility costs after the changes have been made under the contract. Such savings shall be calculated in comparison to an established baseline of utility costs.

(c) "Established baseline" means the precontract utilities, operations, and maintenance costs.

(d) "Utility cost-savings measure" means a measure that produces utility cost savings and/or operation and maintenance cost savings.

(e) "Operation and maintenance cost savings" means a measurable decrease in operation and maintenance costs that is a direct result of the implementation of one or more utility cost-savings measures but does not include savings from in-house staff labor. Such savings shall be calculated in comparison to an established baseline of operation and maintenance costs.

(f) "Guaranteed savings contract" means a contract for the evaluation, recommendation, and installation of one or more utility cost-savings measures. The contract must provide that all payments are to be made over time but not to exceed ten years from the date of final installation, and the savings are guaranteed to the extent necessary to make payments for the utility cost-savings measures.

(g) "Baseline adjustments" means adjusting the established baselines in paragraphs (b) and (d) for changes in the following variables:

(1) utility rates;

(2) number of days in the utility billing cycle;

(3) square footage of the facility;

(4) operational schedule of the facility;

(5) facility temperature set points;

(6) weather; and

(7) amount of equipment or lighting utilized in the facility.

(h) "Lease purchase contract" means a contract obligating the state to make regular lease payments to satisfy the lease costs of the utility cost-savings measures until the final payment, after which time the utility cost-savings measures become the sole property of the state of Minnesota.

(i) "Qualified provider" means a person or business experienced in the design, implementation, and installation of utility cost-savings measures.

(j) "Engineering report" means a report prepared by a professional engineer licensed by the state of Minnesota summarizing estimates of all costs of installations, modifications, or remodeling, including costs of design, engineering, installation, maintenance, repairs, and estimates of the amounts by which utility and operation and maintenance costs will be reduced.

(k) "Capital cost avoidance" means money expended by a state agency to pay for utility cost-savings measures with a guaranteed savings contract so long as the measures that are being implemented to achieve the cost savings are a significant portion of an overall project.

(l) "Guaranteed savings contracting guidelines" means policies, procedures, and requirements of guaranteed savings contracts established by the Department of Administration upon enacting this legislation.

Subd. 2. Guaranteed savings contract. The commissioner may enter into a guaranteed savings contract with a qualified provider if:

(1) the qualified provider is selected through a competitive process in accordance with the guaranteed savings contracting guidelines within the Department of Administration;

(2) the qualified provider agrees to submit an engineering report prior to the execution of the guaranteed savings contract;

(3) the commissioner finds that the amount it would spend on the utility cost-savings measures recommended in the engineering report will not exceed the amount to be saved in utility operation and maintenance costs over ten years from the date of implementation of utility cost-savings measures;

(4) the qualified provider provides a written guarantee that the utility, operation, and maintenance cost savings will meet or exceed the costs of the guaranteed savings contract. The qualified provider shall reimburse the state for any shortfall of guaranteed utility cost savings; and

(5) the qualified provider gives a sufficient bond in accordance with section 574.26 to the commissioner for the faithful implementation and installation of the utility cost-savings measures.

Subd. 3. Lease purchase contract. The commissioner may enter into a lease purchase agreement with any party for the implementation of utility cost-savings measures in accordance with an engineering report. The implementation costs of the utility cost-savings measures recommended in the engineering report shall not exceed the amount to be saved in utility and operation and maintenance costs over the term of the lease purchase agreement. The term of the lease purchase agreement shall not exceed ten years. The lease is assignable in accordance with terms approved by the commissioner of finance.

Subd. 4. Use of capital cost avoidance. The affected state agency may contribute funds for capital cost avoidance for guaranteed savings contracts. Use of capital cost avoidance is subject to the guaranteed savings contracting guidelines within the Department of Administration.

Subd. 5. Report. By January 15 of 2005 and 2007, the commissioner of administration shall submit to the commissioner of finance and the chairs of the senate and house of representatives capital investment committees a list of projects in the agency that have been funded using guaranteed energy savings, as outlined in this section, during the preceding biennium. For each guaranteed savings contract entered into, the commissioner of administration shall contract with an independent third party to evaluate the cost-effectiveness of each utility cost-savings measure implemented to ensure that such measures were the least-cost measures available. For the purposes of this section, "independent third party" means an entity not affiliated with the qualified provider, that is not involved in creating or providing conservation project services to that provider, and that has expertise (or access to expertise) in energy savings practices.

Subd. 6. Contract limits. Contracts may not be entered into after June 30, 2007.

HIST: 1Sp2003 c 8 art 1 s 9

Official Publication of the State of Minnesota