A utility required to report under part 7610.0300 shall estimate the additional power plants or additions to existing plants necessary to provide for the energy growth predicted by the forecasts in parts 7610.0300 to 7610.0320. A utility shall supply the following information about each additional plant or addition:
the proposed general location of each plant currently in the planning stage, or the actual location of each plant currently under construction;
the estimated total annual net megawatt hours generated for nonplant use by the plant operating at normal conditions under normal maintenance and circumstances, during its first full calendar year of operation;
the estimated type and amount of fuel to be used to operate the plant on an annual basis under conditions set forth in item E; and
MS s 216C.10
L 1987 c 312 art 1 s 9; 16 SR 1400