An owner or operator may store petroleum contaminated soil for up to ten days without run-off controls within an approved land treatment plot. After ten days an owner or operator shall spread the batch of petroleum contaminated soil in accordance with part 7037.2300 or take measures to control run-off as provided in items A and B:
covering with a tarpaulin, reinforced plastic which is at least six mils thick, or unreinforced plastic which is at least ten mils thick; or
placing on the perimeter of the stockpile either straw bales or silt dams made of a geotextile material and secured with stakes.
MS s 116.07
17 SR 2914
November 3, 1998
Official Publication of the State of Minnesota