7854.1200 DELAY IN CONSTRUCTION.

If the permittee has not commenced construction of the project within two years after issuance of the site permit, the permittee must advise the commission of the reasons construction has not commenced. In such event, the commission may determine whether the permit should be revoked. No revocation of a permit for failure to commence construction may be undertaken except in accordance with part 7854.1300, subpart 4.

Statutory Authority:

MS s 116C.695; 216F.05

History:

26 SR 1394; L 2005 c 97 art 3 s 19

Published Electronically:

September 18, 2009