When the Public Utilities Commission has issued a Certificate of Need for a large electric power generating plant or a high voltage transmission line or placed a high voltage transmission line on the certified HVTL list maintained by the commission, questions of need, including size, type, and timing, questions of alternative system configurations, and questions of voltage shall not be factors considered by the commission in deciding whether to issue a permit for a proposed facility.
27 SR 1295; L 2005 c 97 art 3 s 19
This part is repealed effective July 1, 2025. L 2024 c 126 art 7 s 15; L 2024 c 127 art 43 s 15.