7850.1400 SMALL PROJECTS.
§
Subpart 1.
No PUC permit required.
A permit from the PUC is not required to construct a power plant of less than 50 megawatts or a transmission line of less than 100 kilovolts. Proposers of such projects must obtain whatever approvals may be required by local, state, or federal units of government with jurisdiction over the project.
History:
27 SR 1295; L 2005 c 97 art 3 s 19
Published Electronically:
October 13, 2009
Official Publication of the State of Minnesota