7835.2900 INTERCONNECTION PLAN.

The utility may require the qualifying facility to submit an interconnection plan not more than 30 days prior to interconnection in order to facilitate interconnection arrangements. If such a plan is required, it must include no more than:

A.

technical specifications of equipment;

B.

proposed date of interconnection; and

C.

projection of net output or consumption by the qualifying facility when available.

Statutory Authority:

MS s 216A.05; 216B.08; 216B.164

History:

9 SR 993

Published Electronically:

February 28, 2000