7835.0300 FILING DATES.

Within 60 days after the effective date of this chapter, on January 1, 1985, and every 12 months thereafter, each utility must file with the commission, for its review and approval, a cogeneration and small power production tariff. The tariff for generating utilities must contain schedules A to G, except that generating utilities with less than 500,000,000 kilowatt-hour sales in the calendar year preceding the filing may substitute their retail rate schedules for schedules A and B. The tariff for nongenerating utilities must contain schedules C, D, E, F, and H, and may, at the option of the utility, contain schedules A and B, using data from the utility's wholesale supplier.