If casing is used in a temporarily sealed exploratory boring, the casing must be:
All casing must be watertight throughout its length, with threaded, solvent welded, or welded joints. Recessed couplings, reamed and drifted couplings, integral flush-threads, or other couplings that match the design, taper, and thread type of the casing must be used on threaded casing. Thread must not be exposed on the exterior of the pipe when the casing is joined to the coupling or when the pipe sections are joined together.
Casing installed in a temporarily sealed exploratory boring must be new casing produced to specifications. Casing removed from an exploratory boring is acceptable for reuse in an exploratory boring if the casing meets the specifications for new casing.
Casing must be marked by the manufacturer according to casing specifications in subparts 15 to 18. Markings must be rolled, stamped, or stenciled by the manufacturer.
Casing rejected by the manufacturer must not be used. The commissioner may require that casing be submitted to an independent testing agency to evaluate whether it meets or exceeds specifications when the casing:
The commissioner shall reject casing if:
the lot of casing contains defective lengths, including casing with girth-welded joints or casing with welded patches.
Casing that is installed during drilling, sometimes referred to as surface casing, and that is removed upon completion of drilling is not required to meet the specifications for casing in subparts 15 to 18, but must be of sufficient strength to withstand the structural load imposed by conditions both inside and outside the exploratory boring.
An outer casing installed in unconsolidated materials is not required to meet the specifications for casing in subparts 15 to 18 if:
the casing is of sufficient strength to withstand the structural load imposed by conditions both inside and outside the boring;
The annular space between an inner casing and an outer casing must be grouted for its entire length by pumping neat cement grout through a tremie pipe, a drill rod, or the casing as specified in part 4727.0980.
All casings of a temporarily sealed exploratory boring must extend vertically at least one foot above the established ground surface and at least five feet above the regional flood level. The established ground surface immediately adjacent to the casing must be graded to divert water away from the casing. Termination of the top of the casing below the established ground surface, such as in a vault or pit, is prohibited.
An exploratory boring that is temporarily sealed must be cased according to items A to C. Borings that flow must meet the special requirements in part 4727.0985.
A boring that terminates in unconsolidated materials must be cased from a point one foot above the established ground surface and at least five feet above the regional flood level to the bottom of the boring.
A boring that terminates in igneous or metamorphic bedrock must be cased from a point one foot above the established ground surface and at least five feet above the regional flood level into igneous or metamorphic bedrock.
A boring that terminates in sedimentary bedrock must be cased from a point of one foot above the established ground surface and at least five feet above the regional flood level into sedimentary bedrock. When a confining layer is encountered, the boring must be cased according to part 4727.0975.
The casing of a temporarily sealed exploratory boring must be covered with a water tight and insect-proof cap or cover equivalent to the casing in weight and strength consisting of:
The casing of an exploratory boring that is temporarily sealed must be protected by at least one of the following methods:
surrounding the casing with a concrete pyramid or cone that has horizontal dimensions of at least 24 inches by 24 inches at the established ground surface, rises 12 inches above the established ground surface at the casing, and has a base with a volume of at least three cubic feet below the established ground surface;
installing a steel outer protective casing meeting the specifications of subpart 15 that is at least 3.25 inches in diameter larger than the inner casing, extends at least two feet above the established ground surface and four feet below the established ground surface, and has neat cement grout or concrete grout in the annular space between the casings from the bottom of the outer protective casing to the established ground surface;
placing three posts at least four inches square or four inches in diameter around the boring at equal distances from each other and two feet from the exploratory boring. The posts must extend two feet above the established ground surface and four feet below the established ground surface, or to a depth of two feet if each post is set in concrete to a depth of two feet. The posts must be made of reinforced concrete, decay-resistant wood, or steel pipe meeting the specifications of subpart 15. Steel pipe must be covered with an overlapping, threaded, or welded steel or iron cap or be filled with concrete or cement; or
extending the casing vertically at least four feet above the established ground surface and reporting the accurate location of the exploratory boring on the temporary sealing report. The location must be determined and reported by using either a differential global positioning system or a survey with bearings and distances taken from property corners or a permanent survey control point.
Steel casing used in the construction of a temporarily sealed exploratory boring must be produced to the following specifications:
DCDMA Technical Manual, section B designations C80, R80, or RC100, and section D flush joint casing standards; or
Steel casing must have the minimum weights and thicknesses specified in this item, subject to the tolerance in the specifications in item A.
Size in Inches | Plain End | Wgt. Lbs. Per Ft. Thrds. & Cplgs.* |
Thrds. R&D Cplgs. | Thickness in Inches | |
S | 1 | 1.68 | 1.68 | 1.70 | .133 |
c | 1-1/4 | 2.27 | 2.28 | 2.30 | .140 |
h | 1-1/2 | 2.72 | 2.73 | 2.75 | .145 |
e | 2 | 3.65 | 3.68 | 3.75 | .154 |
d | 2-1/2 | 5.79 | 5.82 | 5.90 | .203 |
u | 3 | 7.58 | 7.62 | 7.70 | .216 |
l | 3-1/2 | 9.11 | 9.20 | 9.25 | .226 |
e | 4 | 10.79 | 10.89 | 11.00 | .237 |
5 | 14.62 | 14.81 | 15.00 | .258 | |
4 | 6 | 18.97 | 19.18 | 19.45 | .280 |
0 | 8 | 28.55 | 29.35 | .322 | |
10 | 40.48 | 41.85 | .365 | ||
S | 12 | 49.56 | 51.15 | .375 | |
t | 14 | 54.57 | 57.00 | .375 | |
a | 16 | 62.58 | 65.30 | .375 | |
n | 18 | 70.59 | 73.00 | .375 | |
d | 20 | 78.60 | 81.00 | .375 | |
a | 22 | 86.61 | .375 | ||
r | 24 | 94.62 | .375 | ||
d | 26 | 102.63 | .375 | ||
30 | 118.65 | .375 | |||
W | 32 | 126.66 | .375 | ||
g | 34 | 134.67 | .375 | ||
t | 36 | 142.68 | .375 |
* Nominal weight based on length of 20 feet including coupling.
Steel casing up to ten inches in diameter must be Schedule 40. Larger diameter casing must be standard weight.
Diameter-Inches | Couplings | |||
External | Internal | Thrds. per Inch | Minimum External Diameter Inches | Minimum Length Inches |
1.315 | 1.049 | 11-1/2 | 1.576 | 2-5/8 |
1.660 | 1.380 | 11-1/2 | 1.900 | 2-3/4 |
1.900 | 1.610 | 11-1/2 | 2.200 | 2-3/4 |
2.375 | 2.067 | 11-1/2 | 2.750 | 2-7/8 |
2.875 | 2.469 | 8 | 3.250 | 3-15/16 |
3.500 | 3.068 | 8 | 4.000 | 4-1/16 |
4.000 | 3.548 | 8 | 4.625 | 4-3/16 |
4.500 | 4.026 | 8 | 5.200 | 4-5/16 |
5.563 | 5.047 | 8 | 6.296 | 4-1/2 |
6.625 | 6.065 | 8 | 7.390 | 4-11/16 |
8.625 | 7.981 | 8 | 9.625 | 5-1/16 |
10.750 | 10.020 | 8 | 11.750 | 5-9/16 |
12.750 | 12.000 | 8 | 14.000 | 5-15/16 |
14.000 | 13.250 | 8 | 15.000 | 6-3/8 |
16.000 | 15.250 | 8 | 17.000 | 6-3/4 |
18.000 | 17.250 | 8 | 19.000 | 7-1/8 |
20.000 | 19.250 | 8 | 21.000 | 7-5/8 |
22.000 | 21.250 | |||
24.000 | 23.250 | |||
26.000 | 25.250 | |||
30.000 | 29.250 | |||
32.000 | 31.250 | |||
34.000 | 33.250 | |||
36.000 | 35.250 |
Stainless steel casing used in the construction of a temporarily sealed exploratory boring must meet ASTM Standard A312-86a and meet at least:
Plastic casing and couplings used in the construction of a temporarily sealed exploratory boring must:
In addition to plastic couplings approved under subpart 17, couplings meeting the following requirements are also approved:
couplings with socket dimensions meeting the requirements of ASTM Standard F480-88, Table 3; and
ANSI Schedule 40, four-inch and five-inch diameter slip x female thread and five-inch diameter slip x male thread couplings meeting the requirements of ASTM Standard D2466-90a.
All plastic casings, couplings, components, and related joining materials, including solvents, cements, or primers, used in the construction of a temporarily sealed exploratory boring must conform with the requirements of NSF Standard 61-1991 or the health effects portion of NSF Standard 14-1990 and be tested as conforming by an agency certified by ANSI. Conformance to the NSF standard must be coded, stamped, or marked on the casings, couplings, and components, as well as on the containers of related joining materials, including solvents, cements, or primers.
When preparing to install plastic casing, a person must:
inspect casing and couplings carefully for cuts, gouges, deep scratches, damaged ends, and other major imperfections. Any plastic casing or coupling having such defects or imperfections shall not be used;
use solvent cement meeting the requirements of the specifications for the plastic that will be used;
use plastic couplings with molded or formed threads and thread lubricants suitable for the plastic material that will be used.
When cutting plastic casing, casing ends must be cut square using fine-tooth blades with little or no set or a plastic pipe cutter equipped with extra wide rollers and thin cutting wheels. Standard steel pipe or tubing cutters must not be used for cutting plastic casing.
All dirt, dust, and moisture must be cleaned from casing ends and couplings using chemical or mechanical cleaners suitable for the particular plastic material. All burrs must be removed from casing ends and couplings.
An even coat of solvent cement must be applied to the inside of the couplings to cover the distance of the joining surface only. An even coat of solvent cement must then be applied to the outside of the casing being joined to a distance equal to the depth of the casing coupling socket.
When assembling plastic casing, a person must:
turn the casing to evenly distribute the solvent cement while inserting the coupling into the coupling socket;
A person must not drill inside plastic casing. Drilling tools such as drill bits must not be inserted in plastic casing.
Plastic casing must not be used as an outside casing in exploratory borings cased more than five feet into limestone or dolomite bedrock. In limestone or dolomite bedrock, plastic casing may be used as an inner casing if surrounded by an outer steel casing.
MS s 103I.101
28 SR 147
September 15, 2003
Official Publication of the State of Minnesota
Revisor of Statutes