For each project other than a project in a single-family residence executed by the domiciled owner of the residence, the person performing abatement must prepare a project-specific asbestos project plan.
The person performing abatement must have a complete and current asbestos project plan available for inspection at the project site at the start of the project.
The asbestos project plan must contain:
the amount and type of asbestos-containing material to be removed, encapsulated, or enclosed in each asbestos work area;
the date when the heating, ventilating, and air conditioning (HVAC) system for each asbestos work area will be shut down;
the rated capacity of each negative air machine used to establish and maintain the negative air pressure of each containment;
the calculation showing the number of containment air changes per hour and the number of negative air machines used to establish and maintain the required containment negative air pressure for each containment;
documentation if a negative air system is to be exhausted indoors, why it is technically infeasible to exhaust the negative air system outdoors; and
If any information was estimated or a change occurs during the project, the new information must be added to the asbestos project plan as it becomes known.
20 SR 2765
June 3, 2013
Official Publication of the State of Minnesota