2890.3700 DRILLING MOBILIZATION/DEMOBILIZATION AND DRILL CREW PER DIEM FOR TECHNOLOGIES OTHER THAN DIRECT PUSH.

The following tasks have a maximum cost as listed in items A to D when one of these technologies is used: hollow-stem auger, mud or air rotary, air coring, or rotosonic, or when the tasks are necessary for well sealing:

A.

mobilization/demobilization (drilling) (0 to 50 miles one way), $532;

B.

mobilization/demobilization (drilling) (51 to 500 miles one way), $532 plus $9 per mile over 50 miles;

C.

mobilization/demobilization (drilling) (over 500 miles one way), $4,126; and

D.

per diem, $180 per day per person.

Statutory Authority:

MS s 115C.07

History:

28 SR 383; L 2010 c 241 s 4; MS s 115C.07 subd 3 paragraph (f); 28 SR 383; L 2010 c 241 s 4; MS s 115C.07 subd 3 paragraph (f)

Published Electronically:

July 5, 2017