7017.1180 QUALITY CONTROL REPORTING AND NOTIFICATION REQUIREMENTS FOR CEMS.

Subpart 1.

Cylinder gas audit summary.

A cylinder gas audit summary must be submitted on a form approved by the commissioner within 30 days following the end of the calendar quarter in which the audit was completed. Any such form provided by the commissioner shall only seek information relevant to the cylinder gas audit.

Subp. 2.

Relative accuracy test audit notification.

The owner or operator shall notify the commissioner in writing at least 30 days prior to conducting any relative accuracy test audit. The notification may be made by facsimile, mail, electronic mail, or hand-delivered document.

Subp. 3.

Relative accuracy test audit summary.

A relative accuracy test audit summary report must be submitted on a form approved by the commissioner within 30 days following the end of the calendar quarter in which the relative accuracy test audit was conducted. Any such form provided by the commissioner shall only seek information relevant to the relative accuracy test audit.

Subp. 4.

Linearity check results summary.

Facilities subject to Code of Federal Regulations, title 40, part 75, shall submit a linearity check summary within 30 days following the end of the calendar quarter in which the linearity check was conducted on a form approved by the commissioner. Any such form provided by the commissioner shall only seek information relevant to the linearity check.