The notification required for field-erected tanks is as described in items A to C.
Except as provided in item B, the permittee shall notify the commissioner, in writing, at least 60 days prior to implementation of any of the following:
The permittee need not notify the commissioner of any construction or installation of a type listed in item A which is specifically required by the permit or excluded by the terms and conditions of the permit.
The permittee shall obtain the commissioner's written approval prior to placing any new field-erected tank or underground transmission line into service, returning to service any field-erected tank closed at the time of issuance of the permit, or deviating from schedules contained in the permit. The commissioner shall respond, in writing, within 30 days of receipt of the permittee's written request.
MS s 115.03
23 SR 883