16C.31 Design-build contracts.

Subdivision 1. General authority. (a) Notwithstanding section 16C.03, subdivision 3, the commissioner may solicit and award a design-build contract between the commissioner and a design-builder utilizing the competitive acquisition process described in subdivisions 5 through 9 if the commissioner meets the conditions in paragraph (b). A design-build contract may provide the architectural, engineering, and related design services as well as the labor, materials, supplies, equipment, and construction services for a project. A design-build contract may include telecommunications cabling but must not include acquisition of personal property related to the operations of the occupants. The commissioner may make changes to the project without invalidating the design-build contract.

(b) The commissioner shall, for each project for which the commissioner intends to use the design-build method, make a written determination that it is in the best interest of the state to use the design-build method to complete the project. In making this determination, the commissioner shall use the following criteria as the minimum basis for the determination:

(1) the extent to which the project requirements can be adequately defined in a request for proposal before completing the design process;

(2) the suitability of the delivery method with respect to scope, schedule, cost, and quality factors;

(3) the suitability of the delivery method to minimize life-cycle costs to the extent available within the project budget;

(4) the suitability of the delivery method to efficiently achieve functionality requirements;

(5) the impact of the project schedule on the agency's delivery of services and project cost;

(6) the resources of the department of administration to manage the project through employment of experienced personnel or hiring of consultants;

(7) the resources of the department of administration to oversee the project with persons who are familiar and experienced with the design-build method of project delivery or similar experience; and

(8) other criteria that the commissioner deems relevant and that are included in the written determination.

(c) The authority and duties prescribed for the board, the commissioner, and department of administration under this section are granted to and must be performed by the board of regents of the University of Minnesota and the board of trustees of the Minnesota state colleges and universities on projects under their control.

Subd. 2. Licensing requirements. (a) Each design-builder shall be, employ, or have as a partner, member, coventurer, or subcontractor, persons duly licensed, certified, or registered to provide the services required to complete the project and do business in this state.

(b) A design-builder may contract with the commissioner to provide professional or construction services that the design-builder is not itself licensed, certified, registered, or qualified to perform, so long as the design-builder provides the services through subcontracts with duly licensed, certified, or registered, or otherwise qualified persons in accordance with this section.

(c) Nothing in this section authorizing design-build contracts is intended to limit or eliminate the responsibility or liability owed by a professional on a design-build project to the state or other third parties under existing law. The design service portion of a design-build contract is considered a service and not a product.

Subd. 3. University of Minnesota and Minnesota state colleges and universities selection process. (a) The board of regents of the University of Minnesota and the board of trustees of the Minnesota state colleges and universities shall select design-builders for all design-build projects under their supervision and control and funded by the state following the procedures and performing the duties prescribed for the board and commissioner in subdivisions 5 through 9. The board of regents and the board of trustees shall either use the board or establish an evaluation team of at least seven persons to evaluate and recommend design-builders under this section to include three persons selected as provided in paragraph (b). The final selection must be made by the board of regents or the board of trustees.

(b) Upon written request from the board of regents or the board of trustees, each of the following three organizations shall nominate one individual whose name and qualifications must be submitted to the board of trustees for consideration: the Consulting Engineers Council of Minnesota after consultation with other professional engineering societies in the state; the AIA Minnesota; and the Minnesota chapter of the Associated General Contractors after consultation with other commercial contractor associations in the state. The board of regents or the board of trustees may appoint the three named individuals to the evaluation team or reject a nominated individual and request another nomination. The board of regents or the board of trustees shall determine the term of the appointment. The other members of the evaluation team must be representatives of the University of Minnesota or the Minnesota state colleges and universities. The interviews are public meetings and a video or audio recording of the meetings must be made and is public information. The final recommendations and rankings must be in writing.

Subd. 4. Development of design criteria. (a) Each request for proposals for a design-build contract must contain design criteria prepared by a design criteria professional who holds licenses or certifications under sections 326.02 to 326.15 and is either an employee of the state, the University of Minnesota, or a consultant hired by the commissioner. If the design criteria professional is a consultant hired by the state, the licensure requirement may be met by employing individuals who hold a license or licenses under sections 326.02 to 326.15. The commissioner may elect to designate the board to select the consultant in compliance with section 16B.33.

(b) Design criteria set forth in the request for proposals must specify all information needed to adequately describe the project, including performance-based criteria such as sustainability and life-cycle costing requirements; interior space requirements, including adjacency diagrams; material quality standards; architectural image and building form standards; building air quality requirements; commissioning requirements; building burn-in requirements; cost estimates; design and construction schedules; site development requirements; utility requirements; storm water retention and disposal requirements; and parking requirements. If necessary to adequately describe the project, the design criteria must include a boundary and topographic survey of the site, with the legal description and geotechnical and environmental information concerning the site.

(c) There must be an owner's representative for each design-build project. The owner's representative must be either an employee of the state, University of Minnesota, or a consultant hired by the commissioner. Subject to the minimum requirements of paragraphs (a) and (b), the commissioner, in consultation with the agency, the owner's representative, and the design criteria professional, shall determine the scope and level of detail required for the design criteria to be included in the request for proposals.

Subd. 5. Solicitation of proposals. (a) The commissioner shall prepare a request for proposals, which must contain, at a minimum, the following elements:

(1) the identity of the agency that will utilize the completed project;

(2) the procedures for submitting proposals, the criteria for evaluation of proposals and their relative weight for each phase, how those criteria will be scored, and the procedures for making awards;

(3) the terms and conditions for the design-build contract;

(4) the design criteria;

(5) the qualifications the design builder will be required to have;

(6) a request for a critical path method schedule for commencement and completion of the project;

(7) budget limits for the project;

(8) affirmative action, disadvantaged businesses, small business, or set-aside goals or requirements for the design-build contract;

(9) requirements for insurance, performance and payment bonds, bid bonds, and cash deposits;

(10) a description of the drawings, specifications, or other submittals to be submitted with the phase-two proposal, with guidance as to the form and level of completeness of the drawings, specifications, or submittals that will be acceptable;

(11) the professional and technical services contract to be entered into with the design-builders selected to submit phase-two proposals, including scope of work, use of ideas or information, and compensation; and

(12) identification of any other material information available from the commissioner or board, including, without limitation, surveys, soils reports, drawings or models of existing structures, environmental studies, photographs, or references to public records.

(b) The solicitation of request for proposals does not obligate the commissioner to enter into a design-build contract. In accordance with the stated criteria for evaluating proposals, the commissioner may accept or reject any or all proposals received as a result of the request. The notification of rejection of all proposals must include an explanation for all proposals being rejected. The solicitation for proposals may be canceled at any time in the commissioner's sole discretion if it is considered to be in the state's best interest. If the commissioner rejects all proposals or cancels the solicitation for proposals, the commissioner may resolicit a request for proposals using the same or different requirements or request the board to select a designer under section 16B.33 and proceed with the design-bid-build delivery method.

Subd. 6. Qualification; phase-one submittal. (a) In phase one, the board and commissioner shall evaluate the design-build qualifications of the design-builders who responded to the request for proposals with phase-one submittals based on each design-builder's experience, technical competence, and capability to perform; the past performance of the design-builder and its employees, quality control organization and system, sustainability, and life-cycle costing methodology; and other appropriate facts submitted by each design-builder in response to the request for proposals all in accordance with the weighted criteria that are stated for phase-one evaluations in the request for proposals. The phase-one or phase-two evaluation of the "past performance" or "experience" of a proposer must not include the exercise or assertion of a person's legal rights. The board or commissioner may require clarifications from design-builders.

(b) If the project is within the capitol area, the capitol area architecture and planning board, as defined in section 15.50, shall participate in the evaluation of phase-one submittals.

(c) The board shall select to a short list the most qualified design-builders that have responded with phase-one submittals based on the weighted criteria for phase-one evaluations stated in the request for proposals. For projects involving only renovation, in the discretion of the commissioner, the design-builder may be selected only on the phase-one submissions, or after a phase-two submission. For all other projects, the board shall prepare a list of at least three potential design-builders to submit phase-two proposals. The board shall not proceed to obtain phase-two proposals or make a selection, as applicable, unless it receives phase-one submittals from at least three qualified design-builders. If the board receives fewer than three phase-one submittals from qualified design-builders, the commissioner may cancel the solicitation for proposals, revise the request for proposals, and solicit new proposals or request the board to select a designer under section 16B.33 and proceed with the design-bid-build delivery method.

(d) The commissioner shall enter into the professional and technical services contract included in the request for proposals with each of the design-builders qualified by the board to submit phase-two proposals.

Subd. 7. Phase-two proposals. (a) The professional and technical services contract with the design-builders selected to submit phase-two proposals provided in the request for proposals must require at least the following:

(1) preliminary plans and specifications, renderings, and models as may be required in the request for proposals in sufficient detail, to describe the character, quality, and scope of the project;

(2) a design and construction schedule;

(3) the all-inclusive fixed price at which the design-builder will complete the project if the phase-two proposal is accepted, including a total development cost budget in detail by building component with all soft costs, allowances, and design fees; and

(4) other materials the board or commissioner determines are necessary to fix the design, schedule, and cost of the project.

(b) Phase-two proposals must be sealed and may not be opened until expiration of the time established for making proposals as set forth in the request for proposals.

(c) Phase-two proposals must identify each person with whom the design-builder proposes to enter into subcontracts for primary design and construction obligations under the design-build contract. Persons so identified may not be replaced without the approval of the commissioner, or the award may be revoked.

(d) The design-builder must submit a written statement that the phase-two proposal meets all requirements of the request for proposals.

(e) The commissioner may require each design-builder to submit with its phase-one or phase-two proposal, as applicable, a cash deposit or bid bond in the amount of five percent of the budget for the design-build contract. If the phase-one or phase-two proposal, as applicable, is accepted but the design-builder fails to execute the design-build contract, the deposit or bond is forfeited to the extent allowable under law, including the cost to the state of delays, resolicitation, and other results of the failure of the selected design-builder to enter into the design-build contract.

Subd. 8. Stipulated fee. The commissioner may award a stipulated fee not less than two-tenths of one percent of the department's estimated cost of design and construction to each short-listed, responsible proposer who provides a responsive but unsuccessful proposal. If the commissioner does not award a contract, all short-listed proposers may receive the stipulated fee. If the commissioner cancels the contract before reviewing the technical proposals, the commissioner may award each design-builder on the short list a stipulated fee of not less than two-tenths of one percent of the commissioner's estimated cost of design and construction. The commissioner shall pay the stipulated fee, if any, to each proposer within 90 days after the award of the contract or the decision not to award a contract. In consideration for paying the stipulated fee, the commissioner may use any ideas or information contained in the proposals in connection with any contract awarded for the project or in connection with a subsequent procurement, without any obligation to pay any additional compensation to the unsuccessful proposers. Notwithstanding the other provisions of this subdivision, an unsuccessful short-list proposer may elect to waive the stipulated fee. If an unsuccessful short-list proposer elects to waive the stipulated fee, the commissioner may not use ideas and information contained in that proposer's proposal. Upon the request of the commissioner, a proposer who waived a stipulated fee may withdraw the waiver, in which case the commissioner shall pay the stipulated fee, if any, to the proposer and thereafter may use ideas and information in the proposer's proposal.

Subd. 9. Design-builder selection. (a) After obtaining and evaluating proposals from each design-builder according to the criteria and procedures in the request for proposals, the board shall rank the phase-one or phase-two proposals, as applicable, and select the proposal that is rated the highest based on the weighted evaluation criteria in the request for proposal. The board or commissioner may require clarifications from design-builders during the evaluation process. Selection according to this method may result in an award not being made to the lowest cost proposal.

(b) If the project is within the capitol area, the capitol area architectural and planning board shall participate in the evaluation of phase-two proposals.

Subd. 10. Award of design-build contract. If the commissioner decides not to reject all proposals, the commissioner shall award and enter into the design-build contract with the design-builder that submitted the phase-one or phase-two proposal, as applicable, rated highest based on the weighted evaluation criteria as evaluated under the request for qualifications or request for proposals as applicable.

Subd. 11. Expiration. This section expires January 1, 2004.

HIST: 2002 c 393 s 41