161.32 Manner of conducting work on trunk highway.

Subdivision 1. Advertisement for bids. The commissioner may conduct the work or any part thereof incidental to the construction and maintenance of the trunk highways by labor employed therefor or by contract. In cases of construction work, the commissioner shall first advertise for bids for contracts, and if no satisfactory bids are received, may either reject all bids and readvertise, or do the work by labor employed therefor. Except as hereinafter provided, when work is to be done under contract, the commissioner shall advertise for bids once each week for three successive weeks prior to the date such bids are to be received. The advertisement for bids shall be published in a newspaper or other periodical of general circulation in the state. The plans and specifications for the proposed work shall be on file in the commissioner's office prior to the first call for bids.

Subd. 2. Direct negotiation. In cases where the estimated cost of construction work or maintenance work does not exceed $75,000, the commissioner may enter into a contract for the work by direct negotiation, by obtaining two or more quotations for the work, and without advertising for bids or otherwise complying with the requirements of competitive bidding if the total contractual obligation of the state for the directly negotiated contract or contracts on any single project does not exceed $75,000. All quotations obtained shall be kept on file for a period of at least one year after receipt of the quotation.

Subd. 3. Emergencies. In the case of emergency, contracts may be let without advertising for bids. Emergency is defined as a condition on a trunk highway that necessitates immediate work in order to keep such highway open for travel. No such contract shall be let without advertising for bids except upon the written authority of the commissioner or the commissioner's deputy.

Subd. 4. Repair and restoration of trunk highways damaged by spring breakup. Contracts may be let for the repair and restoration of trunk highways damaged by spring breakup upon advertisement for bids and publication thereof in a newspaper or periodical of general circulation for a period of one week prior to the date such bids are to be received, and upon the mailing of such advertisements to all contractors who have filed a written request therefor.

Subd. 5. Default by contractor. In cases where work is being done under contract and the commissioner finds that the contractor has failed to comply within 60 days from the date of receipt of a written demand to make arrangements, satisfactory to the commissioner, to correct specified delays, neglect, or default, within the control of the contractor, the commissioner may negotiate with others, with the approval of the defaulting contractor's surety, for the completion of the contract according to the terms and provisions of the contract.

Subd. 6. Landscape contractors; payment. When goods or services are provided to the commissioner by a landscape contractor for the landscaping of a trunk highway, the commissioner shall agree in the contract to pay the landscape contractor 100 percent of the value of the contract upon completion of the contracted work. The commissioner may require the contractor, as part of the contract, to post a bond for a sum not exceeding 125 percent of the value of the contract, payable to the commissioner, and conditioned upon the work's compliance with the contract terms, for a period of one year beyond the work completion date.

HIST: 1959 c 500 art 2 s 32; 1961 c 17 s 1; 1963 c 455 s 1; 1967 c 232 s 1; 1981 c 209 s 4; 1985 c 76 s 1; 1986 c 444