A generic EIS may be ordered by the EQB to study types of projects that are not adequately reviewed on a case-by-case basis.
The EQB may be the RGU for the generic EIS or may designate another governmental unit to be the RGU, if that governmental unit consents to be the RGU. In determining which governmental unit should be the RGU for a generic EIS, the EQB shall consider the following factors with respect to each prospective RGU:
expertise in the subject matter of the generic EIS, including the ability to address any complex issues;
A governmental unit or any other person may request the EQB to order a generic EIS.
Time deadlines for the preparation of a generic EIS shall be set at the scoping meeting.
In determining the need for a generic EIS, the EQB shall consider:
if the review of a type of action can be better accomplished by a generic EIS than by project specific review;
if the possible effects on the human environment from a type of action are highly uncertain or involve unique or unknown risks;
the degree to which decision makers or the public have a need to be informed of the potential impacts of such projects;
the degree to which information to be presented in the generic EIS is needed for governmental or public planning;
the potential for significant environmental effects as a result of the cumulative impacts of such projects;
the regional and statewide significance of the impacts and the degree to which they can be addressed on a project-by-project basis;
the degree to which governmental policies affect the number or location of such projects or the potential for significant environmental effects;
the degree to which the cost of basic information ought to be borne by the public rather than individual project proposers;
the need to explore issues raised by a type of project that go beyond the scope of review of individual projects; and
the need to understand the long-term past, present, and future effects of a type of action upon the economy, environment, and way of life of the residents of the state.
The generic EIS shall be scoped. Scoping shall be coordinated by the RGU and shall identify the issues and geographic areas to be addressed in the generic EIS. Scoping procedures shall follow the procedures in part 4410.2100 except for the identification of permits for which information is to be gathered concurrently with the EIS preparation, the preparation and circulation of the EAW, and the time requirements.
In addition to content requirements specified by the scoping process, the generic EIS shall contain the following:
any new data that has been gathered or the results of any new research that has been undertaken as part of the generic EIS preparation;
a description of the possible impacts and likelihood of occurrence, the extent of current use, and the possibility of future development for the type of action;
alternatives including recommendations for geographic placement of the type of action to reduce environmental harm, different methods for construction and operation, and different types of actions that could produce the same or similar results as the subject type of action but in a less environmentally harmful manner; and
Preparation of a generic EIS does not exempt specific activities from project-specific environmental review.
The fact that a generic EIS is being prepared shall not preclude the undertaking and completion of a specific project whose impacts are considered in the generic EIS.