Session laws use visual text formatting such as stricken text to denote deleted language, and underlined text to denote new language. For users of the jaws screenreader it is recommended to configure jaws to use the proofreading scheme which will alter the pitch of the reading voice when reading stricken and underlined text. Instructions for configuring your jaws reader are provided by following this link.
If you can not or do not wish to configure your screen reader, deleted language will begin with the phrase "deleted text begin" and be followed by the phrase "deleted text end", new language will begin with the phrase "new text begin" and be followed by "new text end". Skip to text of Chapter 288.

Menu

Revisor of Statutes Menu

Authenticate

Pdf

2010 Minnesota Session Laws

Key: (1) language to be deleted (2) new language

CHAPTER 288--H.F.No. 1182

An act

relating to eminent domain; clarifying use of eminent domain authority by public service corporations; regulating the granting of route permits for high-voltage transmission lines; requiring a report;

amending Minnesota Statutes 2008, sections 117.225; 216E.03, subdivision 7; Minnesota Statutes 2009 Supplement, section 117.189.

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:

Section 1.

Minnesota Statutes 2009 Supplement, section 117.189, is amended to read:

117.189 PUBLIC SERVICE CORPORATION EXCEPTIONS.

Sections 117.031; 117.036; 117.055, subdivision 2, paragraph (b); 117.186; 117.187; 117.188; and 117.52, subdivisions 1a and 4, do not apply to the use of eminent domain authority by public service corporations for any purpose other than construction or expansion of:

(1) a high-voltage transmission line of 100 kilovolts or more, or ancillary substations; or

(2) a natural gas, petroleum, or petroleum products pipeline, or ancillary compressor stations or pumping stations.

For purposes of an award of appraisal fees under section 117.085, the fees awarded may not exceed $1,500 for all types of property except for a public service corporation's use of eminent domain for a high-voltage transmission line, where the award may not exceed $3,000.

For purposes of this section, "pipeline" does not include a natural gas distribution line transporting gas to an end user.

EFFECTIVE DATE.

This section is effective the day following final enactment and applies to eminent domain proceedings or actions commenced on or after that date. "Commenced" means when service of notice of the petition under Minnesota Statutes, section 117.055, is made.

Sec. 2.

Minnesota Statutes 2008, section 117.225, is amended to read:

117.225 EASEMENT DISCHARGE.

Whenever claiming that an easement acquired by condemnation is not being used for the purposes for which it was acquired, the underlying fee owner may apply to the district court of the county in which the land is situated for an order discharging the easement, upon such terms as are just and equitable. Due notice of said application shall be given to all interested parties. Provided, however, this section shall not apply to easements acquired by condemnation by a public service corporation now or hereafter doing business in the state of Minnesota for any purpose other than construction or expansion of:

(1) a high-voltage transmission line of 100 kilovolts or more, including ancillary substations; or

(2) a natural gas, petroleum, or petroleum products pipeline, including ancillary compressor stations or pumping stations.

For purposes of this section, "pipeline" does not include a natural gas distribution line transporting gas to an end user.

EFFECTIVE DATE.

This section is effective the day following final enactment and applies to eminent domain proceedings or actions commenced on or after that date. "Commenced" means when service of notice of the petition under Minnesota Statutes, section 117.055, is made.

Sec. 3.

Minnesota Statutes 2008, section 216E.03, subdivision 7, is amended to read:

Subd. 7.

Considerations in designating sites and routes.

(a) The commission's site and route permit determinations must be guided by the state's goals to conserve resources, minimize environmental impacts, minimize human settlement and other land use conflicts, and ensure the state's electric energy security through efficient, cost-effective power supply and electric transmission infrastructure.

(b) To facilitate the study, research, evaluation, and designation of sites and routes, the commission shall be guided by, but not limited to, the following considerations:

(1) evaluation of research and investigations relating to the effects on land, water and air resources of large electric power generating plants and high-voltage transmission lines and the effects of water and air discharges and electric and magnetic fields resulting from such facilities on public health and welfare, vegetation, animals, materials and aesthetic values, including baseline studies, predictive modeling, and evaluation of new or improved methods for minimizing adverse impacts of water and air discharges and other matters pertaining to the effects of power plants on the water and air environment;

(2) environmental evaluation of sites and routes proposed for future development and expansion and their relationship to the land, water, air and human resources of the state;

(3) evaluation of the effects of new electric power generation and transmission technologies and systems related to power plants designed to minimize adverse environmental effects;

(4) evaluation of the potential for beneficial uses of waste energy from proposed large electric power generating plants;

(5) analysis of the direct and indirect economic impact of proposed sites and routes including, but not limited to, productive agricultural land lost or impaired;

(6) evaluation of adverse direct and indirect environmental effects that cannot be avoided should the proposed site and route be accepted;

(7) evaluation of alternatives to the applicant's proposed site or route proposed pursuant to subdivisions 1 and 2;

(8) evaluation of potential routes that would use or parallel existing railroad and highway rights-of-way;

(9) evaluation of governmental survey lines and other natural division lines of agricultural land so as to minimize interference with agricultural operations;

(10) evaluation of the future needs for additional high-voltage transmission lines in the same general area as any proposed route, and the advisability of ordering the construction of structures capable of expansion in transmission capacity through multiple circuiting or design modifications;

(11) evaluation of irreversible and irretrievable commitments of resources should the proposed site or route be approved; and

(12) when appropriate, consideration of problems raised by other state and federal agencies and local entities.

(c) If the commission's rules are substantially similar to existing regulations of a federal agency to which the utility in the state is subject, the federal regulations must be applied by the commission.

(d) No site or route shall be designated which violates state agency rules.

(e) The commission must make specific findings that it has considered locating a route for a high-voltage transmission line on an existing high-voltage transmission route and the use of parallel existing highway right-of-way and, to the extent those are not used for the route, the commission must state the reasons.

EFFECTIVE DATE.

This section is effective the day following final enactment and applies to route applications filed on and after that date.

Sec. 4.

TRANSMISSION LINE ROUTING.

(a) The Public Utilities Commission and the commissioner of transportation must cooperate to implement the policy in Minnesota Statutes, section 216E.03, subdivision 7, paragraph (e).

(b) The commission must report any statutory amendments required for the implementation of Minnesota Statutes, section 216E.03, subdivision 7, paragraph (e) to the chairs and ranking minority members of the energy and transportation policy committees of the legislature by January 15, 2011.

EFFECTIVE DATE.

This section is effective the day following final enactment.