116C.57 Designation of sites and routes; procedures; considerations; emergency certification; exemption.

Subdivision 1. Site permit. No person may construct a large electric generating plant without a site permit from the board. A large electric generating plant may be constructed only on a site approved by the board. The board must incorporate into one proceeding the route selection for a high voltage transmission line that is directly associated with and necessary to interconnect the large electric generating plant to the transmission system and whose need is certified as part of the generating plant project by the Public Utilities Commission.

Subd. 2. Route permit. No person may construct a high voltage transmission line without a route permit from the board. A high voltage transmission line may be constructed only along a route approved by the board.

Subd. 2a. Application. Any person seeking to construct a large electric power generating plant or a high voltage transmission line must apply to the board for a site or route permit. The application shall contain such information as the board may require. The applicant shall propose at least two sites for a large electric power generating plant and two routes for a high voltage transmission line. The chair of the board shall determine whether an application is complete and advise the applicant of any deficiencies within ten days of receipt. An application is not incomplete if information not in the application can be obtained from the applicant during the first phase of the process and that information is not essential for notice and initial public meetings.

Subd. 2b. Notice of application. Within 15 days after submission of an application to the board, the applicant shall publish notice of the application in a legal newspaper of general circulation in each county in which the site or route is proposed and send a copy of the application by certified mail to any regional development commission, county, incorporated municipality, and township in which any part of the site or route is proposed. Within the same 15 days, the applicant shall also send a notice of the submission of the application and description of the proposed project to each owner whose property is on or adjacent to any of the proposed sites for the power plant or along any of the proposed routes for the transmission line. The notice shall identify a location where a copy of the application can be reviewed. For the purpose of giving mailed notice under this subdivision, owners shall be those shown on the records of the county auditor or, in any county where tax statements are mailed by the county treasurer, on the records of the county treasurer; but other appropriate records may be used for this purpose. The failure to give mailed notice to a property owner, or defects in the notice, shall not invalidate the proceedings, provided a bona fide attempt to comply with this subdivision has been made. Within the same 15 days, the applicant shall also send the same notice of the submission of the application and description of the proposed project to those persons who have requested to be placed on a list maintained by the board for receiving notice of proposed large electric generating power plants and high voltage transmission lines.

Subd. 2c. Environmental review. The board shall prepare an environmental impact statement on each proposed large electric generating plant or high voltage transmission line for which a complete application has been submitted. For any project that has obtained a certificate of need from the Public Utilities Commission, the board shall not consider whether or not the project is needed. No other state environmental review documents shall be required. The board shall study and evaluate any site or route proposed by an applicant and any other site or route the board deems necessary that was proposed in a manner consistent with rules adopted by the board concerning the form, content, and timeliness of proposals for alternate sites or routes.

Subd. 2d. Public hearing. The board shall hold a public hearing on an application for a site permit for a large electric power generating plant or a route permit for a high voltage transmission line. All hearings held for designating a site or route shall be conducted by an administrative law judge from the Office of Administrative Hearings pursuant to the contested case procedures of chapter 14. Notice of the hearing shall be given by the board at least ten days in advance but no earlier than 45 days prior to the commencement of the hearing. Notice shall be by publication in a legal newspaper of general circulation in the county in which the public hearing is to be held and by certified mail to chief executives of the regional development commissions, counties, organized towns, townships, and the incorporated municipalities in which a site or route is proposed. Any person may appear at the hearings and offer testimony and exhibits without the necessity of intervening as a formal party to the proceedings. The administrative law judge may allow any person to ask questions of other witnesses. The administrative law judge shall hold a portion of the hearing in the area where the power plant or transmission line is proposed to be located.

Subd. 3. Repealed, 2001 c 212 art 7 s 36

Subd. 4. Considerations in designating sites and routes. The board's site and route permit determinations must be guided by the state's goals to conserve resources, minimize environmental impacts, minimize human settlement and other land use conflicts, and ensure the state's electric energy security through efficient, cost-effective power supply and electric transmission infrastructure. To facilitate the study, research, evaluation and designation of sites and routes, the board shall be guided by, but not limited to, the following considerations:

(1) Evaluation of research and investigations relating to the effects on land, water and air resources of large electric power generating plants and high voltage transmission lines and the effects of water and air discharges and electric and magnetic fields resulting from such facilities on public health and welfare, vegetation, animals, materials and aesthetic values, including baseline studies, predictive modeling, and evaluation of new or improved methods for minimizing adverse impacts of water and air discharges and other matters pertaining to the effects of power plants on the water and air environment;

(2) Environmental evaluation of sites and routes proposed for future development and expansion and their relationship to the land, water, air and human resources of the state;

(3) Evaluation of the effects of new electric power generation and transmission technologies and systems related to power plants designed to minimize adverse environmental effects;

(4) Evaluation of the potential for beneficial uses of waste energy from proposed large electric power generating plants;

(5) Analysis of the direct and indirect economic impact of proposed sites and routes including, but not limited to, productive agricultural land lost or impaired;

(6) Evaluation of adverse direct and indirect environmental effects that cannot be avoided should the proposed site and route be accepted;

(7) Evaluation of alternatives to the applicant's proposed site or route proposed pursuant to subdivisions 1 and 2;

(8) Evaluation of potential routes that would use or parallel existing railroad and highway rights-of-way;

(9) Evaluation of governmental survey lines and other natural division lines of agricultural land so as to minimize interference with agricultural operations;

(10) Evaluation of the future needs for additional high voltage transmission lines in the same general area as any proposed route, and the advisability of ordering the construction of structures capable of expansion in transmission capacity through multiple circuiting or design modifications;

(11) Evaluation of irreversible and irretrievable commitments of resources should the proposed site or route be approved; and

(12) When appropriate, consideration of problems raised by other state and federal agencies and local entities.

If the board's rules are substantially similar to existing regulations of a federal agency to which the utility in the state is subject, the federal regulations must be applied by the board.

No site or route shall be designated which violates state agency rules.

Subd. 5. Repealed, 2001 c 212 art 7 s 36

Subd. 5a. Repealed, 2001 c 212 art 7 s 36

Subd. 6. Recording of survey points. The permanent location of monuments or markers found or placed by a utility in a survey of right-of-way for a route shall be placed on record in the office of the county recorder or registrar of titles. No fee shall be charged to the utility for recording this information.

Subd. 7. Timing. The board shall make a final decision on an application within 60 days after receipt of the report of the administrative law judge. A final decision on the request for a site permit or route permit shall be made within one year after the chair's determination that an application is complete. The board may extend this time limit for up to three months for just cause or upon agreement of the applicant.

Subd. 8. Final decision. (a) No site permit shall be issued in violation of the site selection standards and criteria established in this section and in rules adopted by the board. When the board designates a site, it shall issue a site permit to the applicant with any appropriate conditions. The board shall publish a notice of its decision in the State Register within 30 days of issuance of the site permit.

(b) No route permit shall be issued in violation of the route selection standards and criteria established in this section and in rules adopted by the board. When the board designates a route, it shall issue a permit for the construction of a high voltage transmission line specifying the design, routing, right-of-way preparation, and facility construction it deems necessary, and with any other appropriate conditions. The board may order the construction of high voltage transmission line facilities that are capable of expansion in transmission capacity through multiple circuiting or design modifications. The board shall publish a notice of its decision in the State Register within 30 days of issuance of the permit.

HIST: 1973 c 591 s 7; 1975 c 271 s 6; 1977 c 439 s 10; 1986 c 444; 1987 c 384 art 2 s 21; 1989 c 346 s 1; 1994 c 644 s 1; 2000 c 289 s 1; 2001 c 212 art 7 s 5-13