16C.095 SELECTION OF CERTAIN PROFESSIONAL SERVICE CONTRACTORS.
    Subdivision 1. Professional services covered. This section applies to an agency contract
for professional services of persons regulated by the Board of Architecture, Engineering, Land
Surveying, Landscape Architecture, Geoscience, and Interior Design for which the agency, with
the approval of the commissioner, decides to use procedures under this section. If the agency,
with the approval of the commissioner, decides to use procedures under this section, it must
comply with subdivisions 2, 3, and 4. This section does not apply to an agency contract that is
subject to section 16B.33.
    Subd. 2. Qualification-based selection. Notwithstanding section 16C.06, subdivision 6, an
agency must rank contractors described in subdivision 1 on the basis of qualifications, as described
in subdivision 3, for the type of professional service required. An agency may solicit pricing
information from a single responder at a time in rank order, commencing with the highest ranked
contractor, to determine contractor compensation only after the agency has ranked prospective
contractors based on the factors the agency specifies in accordance with subdivisions 3 and 4.
    Subd. 3. Procedures. Subject to subdivision 2, procedures for screening and selection
of contractors are within the sole discretion of the agency and must be approved by the
commissioner when the agency seeks approval to use this alternative. Procedures may be adjusted
to accommodate the agency's cost, scope, and schedule objectives for a particular project.
Screening and selection procedures may include a consideration of each contractor's:
(1) specialized expertise, capabilities, and technical competence as demonstrated by the
proposed approach and methodology to meet the project requirements;
(2) resources available to perform the work, including any specialized services, within the
specified time limits for the project;
(3) record of past performance, including but not limited to price and cost data from previous
projects, quality of work, ability to meet schedules, cost control, and contract administration;
(4) ownership status and employment practices regarding women, minorities, and emerging
small businesses or historically underutilized businesses;
(5) availability to the project locale;
(6) familiarity with the project locale;
(7) proposed project management techniques; and
(8) ability and proven history in handling special project constraints.
    Subd. 4. Selection. (a) The agency shall rank prospective contractors based on the factors
approved by the commissioner, which the agency must specify in the request for proposal, in
accordance with this section. The agency and the highest ranked contractor shall mutually
discuss and refine the scope of services for the project and shall negotiate conditions, including
but not limited to compensation and performance schedule, based on the scope of the services.
The compensation level paid must be reasonable and fair to the agency, as determined solely
by the agency.
(b) If the agency and the highest ranked contractor are unable for any reason to negotiate a
contract at a compensation level that is reasonable and fair to the agency, the agency shall, either
orally or in writing, terminate negotiations with this contractor. The agency may then negotiate
with the next highest ranked contractor, as provided in this subdivision. The negotiation process
may continue through successive contractors, according to agency ranking, until an agreement is
reached or the agency terminates the contracting process.
History: 2001 c 100 s 1