103F.389 Review and certification of land use actions.

Subdivision 1. Land use actions covered. To ensure that the comprehensive land use plan is not nullified by unjustified exceptions in particular cases and to promote uniformity in the treatment of applications for exceptions, a review and certification procedure is established for the following categories of land use actions taken by the counties and directly or indirectly affecting land use within the area covered by the plan:

(1) the adoption or amendment of an ordinance regulating the use of land, including rezoning of a particular tract of land;

(2) the granting of a variance from provisions of the land use ordinances; and

(3) the approval of a plat which is inconsistent with the land use ordinance.

Subd. 2. Land use actions must be consistent with plan. (a) Notwithstanding any contrary provision of chapter 394, an action of a type specified in subdivision 1, clauses (1) to (3), is not effective until the board has reviewed the action and certified that it is consistent with the comprehensive plan of the board.

(b) In determining consistency of ordinances and ordinance amendments, the provisions of the comprehensive land use plan shall be considered minimum standards. An aggrieved person may appeal a decision of the type specified in subdivision 1, clauses (1) to (3), which is reviewed by the board under this section in the manner provided for review of a decision of a board of adjustment under section 394.27, subdivision 9, but only after the procedures prescribed under this section have been completed.

Subd. 3. Procedure for certification. (a) A copy of all notices of public hearings or, when a hearing is not required, a copy of the application to consider any actions of a type specified in subdivision 1, clauses (1) to (3), must be forwarded to the board by the county at least ten days prior to the hearing or meetings to consider the land use actions.

(b) The county shall notify the board of its final decision on the proposed action within ten days of the decision.

(c) By 30 days from the time it receives the notice, the board shall notify the county and the applicant of its approval or disapproval of the proposed action.

Subd. 4. Disapproval of actions. (a) If the board issues a notice of disapproval, either the county or the applicant may, within 30 days of notice, file a demand for a hearing with the board.

(b) If a demand is not filed during that period, the disapproval becomes final.

(c) If a demand is filed within the 30-day period, a hearing shall be held within 60 days of demand and shall be preceded by two weeks' published notice. Within 30 days after the hearing, the board shall either affirm its disapproval of the proposed action or certify its approval.

HIST: 1990 c 391 art 6 s 54