116C.57 Designation of sites and routes; procedures; considerations; emergency certification; exemption.

Subdivision 1. Designation of sites suitable for specific facilities; reports. A utility must apply to the board in a form and manner prescribed by the board for designation of a specific site for a specific size and type of facility. The application shall contain at least two proposed sites. In the event a utility proposes a site not included in the board's inventory of study areas, the utility shall specify the reasons for the proposal and shall make an evaluation of the proposed site based upon the planning policies, criteria and standards specified in the inventory. Pursuant to sections 116C.57 to 116C.60, the board shall study and evaluate any site proposed by a utility and any other site the board deems necessary which was proposed in a manner consistent with rules adopted by the board concerning the form, content, and timeliness of proposals for alternate sites. No site designation shall be made in violation of the site selection standards established in section 116C.55. The board shall indicate the reasons for any refusal and indicate changes in size or type of facility necessary to allow site designation. Within a year after the board's acceptance of a utility's application, the board shall decide in accordance with the criteria specified in section 116C.55, subdivision 2, the responsibilities, procedures and considerations specified in section 116C.57, subdivision 4, and the considerations in chapter 116D which proposed site is to be designated. The board may extend for just cause the time limitation for its decision for a period not to exceed six months. When the board designates a site, it shall issue a certificate of site compatibility to the utility with any appropriate conditions. The board shall publish a notice of its decision in the State Register within 30 days of site designation. No large electric power generating plant shall be constructed except on a site designated by the board.

Subd. 2. Designation of routes; procedure. A utility shall apply to the board in a form and manner prescribed by the board for a permit for the construction of a high voltage transmission line. The application shall contain at least two proposed routes. Pursuant to sections 116C.57 to 116C.60, the board shall study, and evaluate the type, design, routing, right-of-way preparation and facility construction of any route proposed in a utility's application and any other route the board deems necessary which was proposed in a manner consistent with rules adopted by the board concerning the form, content, and timeliness of proposals for alternate routes provided, however, that the board shall identify the alternative routes prior to the commencement of public hearings thereon pursuant to section 116C.58. Within one year after the board's acceptance of a utility's application, the board shall decide in accordance with the criteria and standards specified in section 116C.55, subdivision 2, and the considerations specified in section 116C.57, subdivision 4, which proposed route is to be designated. The board may extend for just cause the time limitation for its decision for a period not to exceed 90 days. When the board designates a route, it shall issue a permit for the construction of a high voltage transmission line specifying the type, design, routing, right-of-way preparation and facility construction it deems necessary and with any other appropriate conditions. The board may order the construction of high voltage transmission line facilities which are capable of expansion in transmission capacity through multiple circuiting or design modifications. The board shall publish a notice of its decision in the state register within 30 days of issuance of the permit. No high voltage transmission line shall be constructed except on a route designated by the board, unless it was exempted pursuant to subdivision 5.

Subd. 3. Emergency certification. Any utility whose electric power system requires the immediate construction of a large electric power generating plant or high voltage transmission line may make application to the board for an emergency certificate of site compatibility or permit for the construction of high voltage transmission lines, which certificate or permit shall be issued in a timely manner no later than 195 days after the board's acceptance of the application and upon a finding by the board that a demonstrable emergency exists which requires immediate construction, and that adherence to the procedures and time schedules specified in this section would jeopardize the utility's electric power system or would jeopardize the utility's ability to meet the electric needs of its customers in an orderly and timely manner. A public hearing to determine if an emergency exists shall be held within 90 days of the application. The board shall, after notice and hearing, promulgate rules specifying the criteria for emergency certification.

Subd. 4. Considerations in designating sites and routes. To facilitate the study, research, evaluation and designation of sites and routes, the board shall be guided by, but not limited to, the following responsibilities, procedures, and considerations:

(1) Evaluation of research and investigations relating to the effects on land, water and air resources of large electric power generating plants and high voltage transmission line routes and the effects of water and air discharges and electric fields resulting from such facilities on public health and welfare, vegetation, animals, materials and aesthetic values, including base line studies, predictive modeling, and monitoring of the water and air mass at proposed and operating sites and routes, evaluation of new or improved methods for minimizing adverse impacts of water and air discharges and other matters pertaining to the effects of power plants on the water and air environment;

(2) Environmental evaluation of sites and routes proposed for future development and expansion and their relationship to the land, water, air and human resources of the state;

(3) Evaluation of the effects of new electric power generation and transmission technologies and systems related to power plants designed to minimize adverse environmental effects;

(4) Evaluation of the potential for beneficial uses of waste energy from proposed large electric power generating plants;

(5) Analysis of the direct and indirect economic impact of proposed sites and routes including, but not limited to, productive agricultural land lost or impaired;

(6) Evaluation of adverse direct and indirect environmental effects which cannot be avoided should the proposed site and route be accepted;

(7) Evaluation of alternatives to the applicant's proposed site or route proposed pursuant to subdivisions 1 and 2;

(8) Evaluation of potential routes which would use or parallel existing railroad and highway rights-of-way;

(9) Evaluation of governmental survey lines and other natural division lines of agricultural land so as to minimize interference with agricultural operations;

(10) Evaluation of the future needs for additional high voltage transmission lines in the same general area as any proposed route, and the advisability of ordering the construction of structures capable of expansion in transmission capacity through multiple circuiting or design modifications;

(11) Evaluation of irreversible and irretrievable commitments of resources should the proposed site or route be approved; and

(12) Where appropriate, consideration of problems raised by other state and federal agencies and local entities.

(13) If the board's rules are substantially similar to existing rules and regulations of a federal agency to which the utility in the state is subject, the federal rules and regulations shall be applied by the board.

(14) No site or route shall be designated which violates state agency rules.

Subd. 5. Exemption of certain routes. A utility may apply to the board in a form and manner prescribed by the board to exempt the construction of any proposed high voltage transmission line from sections 116C.51 to 116C.69. Within 15 days of the board's receipt of the exemption application, the utility shall publish a notice and description of the exemption application in a legal newspaper of general circulation in each county in which the route is proposed and send a copy of the exemption application by certified mail to the chief executive of any regional development commission, county, incorporated municipality and organized town in which the route is proposed and shall send a notice and description of the exemption application to each owner over whose property the line may run, together with an understandable description of the procedures the owner must follow should that owner desire to object. For the purpose of giving mailed notice under this subdivision, owners shall be those shown on the records of the county auditor or, in any county where tax statements are mailed by the county treasurer, on the records of the county treasurer; but other appropriate records may be used for this purpose. Except as to the owners of tax exempt property or property taxes on a gross earnings basis, every property owner whose name does not appear on the records of the county auditor or the county treasurer shall be deemed to have waived such mailed notice unless that owner has requested in writing that the county auditor or county treasurer, as the case may be, include the owner's name on the records for such purpose. The failure to give mailed notice to a property owner, or defects in the notice shall not invalidate the proceedings, provided a bona fide attempt to comply with this subdivision has been made. If any person who owns real property crossed by the proposed route, or any person owning property adjacent to property crossed by the proposed route, or any affected political subdivision files an objection with the board within 60 days after the board's receipt of the exemption application, the board shall either deny the exemption application or conduct a public hearing. If the board determines that the proposed high voltage transmission line will not create significant human or environmental impact, it may exempt the proposed transmission line with any appropriate conditions, but the utility shall comply with any applicable state rule and any applicable zoning, building and land use rules, regulations and ordinances of any regional, county, local and special purpose government in which the route is proposed. The board may by rule require a fee to pay expenses incurred in processing exemptions. Any fee charged is subject to the conditions of section 116C.69, subdivision 2a.

Subd. 5a. Exemption of certain sites. (a) A utility or person may apply to the board in a form and manner prescribed by the board to exempt the construction at a proposed site of a proposed electric power generating plant with a capacity between 50 and 80 megawatts from the requirements of sections 116C.51 to 116C.69. Within 15 days of the board's receipt of an exemption application, the utility or person shall:

(1) publish a notice and description of the exemption application in a legal newspaper of general circulation in the county of the proposed site;

(2) send a copy of the exemption application by certified mail to the chief executive of counties, home rule charter and statutory cities, and organized towns within ten miles of the proposed site; and

(3) mail to each owner whose property is part of or contiguous to the proposed site a notice and description of the exemption application, together with an understandable description of the procedures the owner must follow should the owner desire to object.

(b) For the purpose of giving mailed notice under this subdivision, owners are the persons or entities shown on the tax records of the county auditor or, in a county where tax statements are mailed by the county treasurer, on the records of the county treasurer, but other appropriate records may be used to identify owners. Except for owners of tax-exempt property or property taxed on a gross earnings basis, a property owner whose name does not appear on the records of the county auditor or the county treasurer is deemed to have waived the mailed notice unless the owner has requested in writing that the county auditor or county treasurer, as the case may be, include the owner's name on the records for that purpose. The failure to give mailed notice to a property owner or defects in the notice does not invalidate the proceedings, if a good faith effort is made to comply with this subdivision.

(c) If a person who owns real property that is part of or contiguous to the proposed site or an affected political subdivision files an objection with the board within 60 days after the board receives an exemption application, the board must either deny the exemption application or conduct a public hearing to determine if the proposed electric power generating plant at the proposed site will cause any significant human or environmental impact.

(d) The board shall require environmental review under chapter 116D to assist in making its determination regarding potential significant human and environmental impact.

(e) If the board determines that the proposed plant has an electric power production capacity less than 80 megawatts and the proposed site will not have a significant human and environmental impact, the board may exempt the construction of the proposed plant at the proposed site from the requirements of sections 116C.51 to 116C.69 with any appropriate conditions.

(f) If an exemption is granted, the utility or person must comply with applicable state rules, local zoning, building, and land use rules, regulations, and ordinances of any regional, county, local, and special purpose governments in which the facility is to be located.

(g) The board may, by rule, require a fee to pay costs incurred in processing exemptions. An estimated cost for processing the exemption application must be discussed with the applicant and be approved by the board when an application is received. The applicant must remit 50 percent of the approved cost within 14 days of acceptance of the application. The balance is due within 30 days after receipt of an invoice from the board. Costs in excess of those approved must be certified by the board and charged to the applicant. Certification is prima facie evidence that the costs are reasonable and necessary. All money received pursuant to this subdivision must be deposited in a special account. Money in the account is appropriated to the board to pay expenses incurred in processing the application and in the event the expenses are less than the fee paid, to refund the excess to the applicant.

Subd. 6. Recording of survey points. The permanent location of monuments or markers found or placed by a utility in a survey of right-of-way for a route shall be placed on record in the office of the county recorder or registrar of titles. No fee shall be charged to the utility for recording this information.

HIST: 1973 c 591 s 7; 1975 c 271 s 6; 1977 c 439 s 10; 1986 c 444; 1987 c 384 art 2 s 21; 1989 c 346 s 1; 1994 c 644 s 1