1505.3020 NEW FACILITIES.

Subpart 1.

Permit required.

No person may construct or operate a new bulk pesticide storage facility without first obtaining a permit under parts 1505.3040 and 1505.3050.

Subp. 2.

Information required before construction.

After being granted a permit by the commissioner, and before beginning construction of the bulk pesticide storage facility, an owner or manager shall submit to the commissioner:

A.

the name, address, and telephone number of the persons who will construct, install, or modify the facility; and

B.

copies of any permits or letters of authorization required by any local unit of government for the construction, installation, or modification of the facility.

Subp. 3.

Compliance within 90 days.

Within 90 days after being granted a permit by the commissioner, a new bulk pesticide storage facility owner or manager shall comply with parts 1505.3010 to 1505.3150.

Subp. 4.

Time extension.

The commissioner shall grant a time extension of up to 180 days for delays due to construction or equipment or material procurement if requested in writing by the facility owner or manager. The commissioner shall set forth in writing the reasons for granting or denying a requested time extension within 15 days of the request.

Statutory Authority:

MS s 18B.06; 18B.14

History:

14 SR 161