Skip to main content Skip to office menu Skip to footer
Capital IconMinnesota Legislature

HF 1062

as introduced - 93rd Legislature (2023 - 2024) Posted on 01/30/2023 02:05pm

KEY: stricken = removed, old language.
underscored = added, new language.

Bill Text Versions

Engrossments
Introduction Posted on 01/30/2023

Current Version - as introduced

Line numbers 1.1 1.2 1.3 1.4
1.5 1.6 1.7 1.8 1.9 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18
1.19

A bill for an act
relating to energy; requiring submission of a decommissioning and demolition
plan for a scheduled retirement of an electric generation facility.

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:

Section 1. new text begin DECOMMISSIONING AND DEMOLITION PLAN FOR COAL-FIRED
PLANT.
new text end

new text begin (a) As a part of the next resource plan filing under Minnesota Statutes, section 216B.2422,
subdivision 2, but no later than December 31, 2025, the public utility that owns an electric
generation facility that is powered by coal, scheduled for retirement in 2028, and located
within the St. Croix National Scenic Riverway must provide, to the extent known, the public
utility's plan and a detailed timeline to decommission and demolish the electric generation
facility and remediate pollution at the electric generation facility site.
new text end

new text begin (b) The public utility must also provide a copy of the plan and timeline to the governing
body of the municipality where the electric generation facility is located on the same date
the plan and timeline are submitted to the Public Utilities Commission.
new text end

new text begin (c) If a resource plan is not filed or required before December 31, 2025, the plan and
timeline must be submitted to the Public Utilities Commission and the municipality as a
separate filing by December 31, 2025.
new text end

new text begin EFFECTIVE DATE. new text end

new text begin This section is effective the day following final enactment.
new text end