as introduced - 93rd Legislature (2023 - 2024) Posted on 03/02/2023 02:12pm
A bill for an act
relating to energy; requiring payment of prevailing wage for construction of certain
electric transmission lines; eliminating certain incumbent electric transmission
owner rights; proposing coding for new law in Minnesota Statutes, chapter 216B;
repealing Minnesota Statutes 2022, section 216B.246.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:
new text begin
For purposes of this section, "electric transmission line"
means a high-voltage transmission line with a capacity of at least 100 kilovolts and any
associated transmission facilities.
new text end
new text begin
A person selected through a federally registered
planning authority competitive selection process to develop, construct, and own an electric
transmission line included in a federally registered planning authority transmission plan
must pay at least the prevailing wage rate, as defined in section 177.42, subdivision 6, to
the person's construction contractors and subcontractors working on the project.
new text end
new text begin
Minnesota Statutes 2022, section 216B.246,
new text end
new text begin
is repealed.
new text end
Repealed Minnesota Statutes: 23-03691
(a) For purposes of this section, the terms defined in this subdivision have the meanings given them.
(b) "Electric transmission line" means a high-voltage transmission line with a capacity of 100 kilovolts or more and associated transmission facilities.
(c) "Incumbent electric transmission owner" means any public utility that owns, operates, and maintains an electric transmission line in this state; any generation and transmission cooperative electric association; any municipal power agency; any power district; any municipal utility; or any transmission company as defined under section 216B.02, subdivision 10.
An incumbent electric transmission owner has the right to construct, own, and maintain an electric transmission line that has been approved for construction in a federally registered planning authority transmission plan and connects to facilities owned by that incumbent electric transmission owner. The right to construct, own, and maintain an electric transmission line that connects to facilities owned by two or more incumbent electric transmission owners belongs individually and proportionally to each incumbent electric transmission owner, unless otherwise agreed upon in writing. This section does not limit the right of any incumbent electric transmission owner to construct, own, and maintain any transmission equipment or facilities that have a capacity of less than 100 kilovolts.
(a) If an electric transmission line has been approved for construction in a federally registered planning authority transmission plan, the incumbent electric transmission owner, or owners if there is more than one owner, shall give notice to the commission, in writing, within 90 days of approval, regarding its intent to construct, own, and maintain the electric transmission line. If an incumbent electric transmission owner gives notice of intent to build the electric transmission line then, unless exempt from the requirements of section 216B.243, within 18 months from the date of the notice described in this paragraph or such longer time approved by the commission, the incumbent electric transmission owner shall file an application for a certificate of need under section 216B.243 or certification under section 216B.2425.
(b) If the incumbent electric transmission owner indicates that it does not intend to build the transmission line, such notice shall fully explain the basis for that decision. If the incumbent electric transmission owner, or owners, gives notice of intent not to build the electric transmission line, then the commission may determine whether the incumbent electric transmission owner or other entity will build the electric transmission line, taking into consideration issues such as cost, efficiency, reliability, and other factors identified in this chapter.