Skip to main content Skip to office menu Skip to footer
Capital IconMinnesota Legislature

SF 42

3rd Engrossment - 87th Legislature (2011 - 2012) Posted on 03/06/2012 01:33pm

KEY: stricken = removed, old language.
underscored = added, new language.
Line numbers 1.1 1.2 1.3 1.4 1.5 1.6
1.7 1.8 1.9 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18 1.19 1.20 1.21 1.22 1.23 1.24 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10 2.11 2.12 2.13
2.14 2.15 2.16 2.17 2.18 2.19 2.20 2.21 2.22 2.23 2.24 2.25 2.26 2.27 2.28 2.29 2.30 2.31 2.32 2.33 2.34 2.35 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 3.11 3.12 3.13 3.14 3.15 3.16 3.17 3.18 3.19 3.20 3.21 3.22 3.23 3.24 3.25 3.26 3.27 3.28 3.29 3.30 3.31 3.32
3.33 3.34 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 4.10 4.11 4.12 4.13 4.14 4.15 4.16 4.17 4.18 4.19 4.20 4.21 4.22 4.23 4.24 4.25 4.26 4.27 4.28 4.29
4.30 4.31 4.32 4.33 4.34 4.35 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 5.10 5.11 5.12 5.13 5.14 5.15 5.16 5.17 5.18 5.19 5.20 5.21 5.22 5.23 5.24 5.25 5.26 5.27 5.28 5.29 5.30 5.31 5.32 5.33 5.34 5.35 5.36 6.1 6.2 6.3 6.4 6.5 6.6 6.7 6.8 6.9 6.10 6.11 6.12 6.13 6.14 6.15 6.16 6.17 6.18 6.19 6.20 6.21 6.22 6.23 6.24 6.25 6.26 6.27 6.28 6.29 6.30 6.31 6.32 6.33 6.34 7.1 7.2 7.3 7.4 7.5 7.6 7.7 7.8 7.9 7.10 7.11 7.12 7.13
7.14 7.15
7.16 7.17 7.18 7.19 7.20 7.21 7.22 7.23 7.24 7.25 7.26 7.27 7.28 7.29 7.30 7.31 7.32 7.33 7.34 7.35 8.1 8.2 8.3 8.4 8.5 8.6 8.7 8.8 8.9 8.10 8.11 8.12 8.13 8.14 8.15 8.16 8.17 8.18 8.19 8.20 8.21 8.22 8.23 8.24 8.25 8.26 8.27 8.28 8.29 8.30 8.31 8.32 8.33 8.34 8.35 8.36 9.1 9.2 9.3 9.4 9.5 9.6 9.7 9.8 9.9 9.10 9.11 9.12 9.13 9.14 9.15 9.16 9.17 9.18 9.19 9.20 9.21 9.22 9.23 9.24 9.25 9.26 9.27 9.28 9.29 9.30 9.31 9.32 9.33 9.34 9.35 9.36 10.1 10.2 10.3 10.4 10.5 10.6
10.7 10.8 10.9 10.10 10.11 10.12 10.13 10.14 10.15 10.16
10.17 10.18
10.19 10.20 10.21 10.22 10.23 10.24 10.25 10.26 10.27 10.28 10.29 10.30 10.31 10.32 10.33 10.34 11.1 11.2 11.3 11.4 11.5 11.6 11.7 11.8 11.9 11.10 11.11 11.12 11.13
11.14 11.15
11.16 11.17 11.18 11.19 11.20 11.21
11.22 11.23 11.24 11.25 11.26 11.27 11.28 11.29
11.30 11.31 11.32 11.33 12.1 12.2
12.3 12.4

A bill for an act
relating to environment; providing for permitting efficiency; modifying
environmental review requirements; amending Minnesota Statutes 2010, sections
84.027, by adding a subdivision; 115.07; 116.03, by adding a subdivision; 116.07,
subdivision 2; 116D.04, subdivisions 2a, 3a, 10; 116D.045, subdivisions 1, 3.

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:

Section 1.

Minnesota Statutes 2010, section 84.027, is amended by adding a
subdivision to read:


new text begin Subd. 14a. new text end

new text begin Permitting efficiency. new text end

new text begin (a) It is the goal of the state that environmental
and resource management permits be issued or denied within 150 days of the submission
of a substantially completed permit application. The commissioner of natural resources
shall establish management systems designed to achieve the goal.
new text end

new text begin (b) The commissioner shall prepare semiannual permitting efficiency reports that
include statistics on meeting the goal in paragraph (a). The reports are due February 1 and
August 1 each year. For permit applications that have not met the goal, the report must
state the reasons for not meeting the goal, steps that will be taken to complete action on
the application, and the expected timeline. In stating the reasons for not meeting the
goal, the commissioner shall separately identify delays caused by the responsiveness of
the proposer, lack of staff, scientific or technical disagreements, or the level of public
engagement. The report must specify the number of days from initial submission of
the application to the day of determination that the application is complete. The report
for the final quarter of the fiscal year must aggregate the data for the year and assess
whether program or system changes are necessary to achieve the goal. The report must
be posted on the department's Web site and submitted to the governor and the chairs and
ranking minority members of the house of representatives and senate committees having
jurisdiction over natural resources policy and finance.
new text end

new text begin (c) The commissioner shall allow electronic submission of environmental review
and permit documents to the department.
new text end

new text begin (d) Beginning July 1, 2011, within 30 days of application for a permit subject to
paragraph (a), the commissioner of natural resources shall notify the project proposer, in
writing, of whether or not the permit application is complete enough for processing. If
the permit is incomplete, the commissioner must identify where deficiencies exist and
advise the applicant on how they can be remedied. A resubmittal of the application begins
a new 30-day review period. If the commissioner fails to notify the project proposer of
completeness within the 30-day period, the application is deemed to be substantially
complete and subject to the 150-day permitting review period in paragraph (a) from the
date it was submitted.
new text end

Sec. 2.

Minnesota Statutes 2010, section 115.07, is amended to read:


115.07 VIOLATIONS AND PROHIBITIONS.

Subdivision 1.

Obtain permit.

new text begin (a) Except as provided in paragraph (b), new text end it deleted text begin shall bedeleted text end
new text begin is new text end unlawful for any person to construct, installnew text begin ,new text end or operate a disposal system, or any part
thereof, until plans deleted text begin therefor shalldeleted text end new text begin and specifications for the disposal system new text end have been
submitted to the agencynew text begin ,new text end unless the agency deleted text begin shall have waived thedeleted text end new text begin waives new text end submission
deleted text begin thereof to itdeleted text end new text begin of the plans and specifications new text end and a written permit deleted text begin therefor shall have beendeleted text end
new text begin for the disposal system is new text end granted by the agency.

new text begin (b) If a person who discharges a pollutant into the waters of the state is required by
statute or rule to obtain a national pollutant discharge elimination system permit or a state
disposal system permit, the person may construct or install, prior to issuance of the permit,
at the person's own risk, a disposal system or any part thereof, unless the action taken:
new text end

new text begin (1) is prohibited by federal law or regulation;
new text end

new text begin (2) is by a municipality constructing a wastewater system with a design capacity of
200,000 gallons per day, or less;
new text end

new text begin (3) is subject to environmental review under chapter 116D, and prohibited from
commencing construction until that process is completed;
new text end

new text begin (4) is subject to a grant or loan agreement under chapter 446A;
new text end

new text begin (5) requires a construction storm water permit under rules of the agency; or
new text end

new text begin (6) requires a subsurface sewage treatment system permit under rules of the agency.
new text end

new text begin The person is prohibited from operating the system or discharging pollutants into
the waters of the state until a written permit for the discharge is granted by the agency
and until plans and specifications for the disposal system have been approved, unless the
agency waives the submission of plans and specifications.
new text end

new text begin (c) new text end For disposal systems operated on streams with extreme seasonal flows, the
agency must allow seasonal permit limits based on a fixed or variable effluent limit when
the municipality operating the disposal system requests them and is in compliance with
agency water quality standards.

Subd. 3.

Permission for extension.

new text begin (a) Except as provided in paragraph (b), new text end it
deleted text begin shall bedeleted text end new text begin is new text end unlawful for any person to make any change in, addition tonew text begin ,new text end or extension of any
existing disposal system or point source, or part thereof, to effect any facility expansion,
production increase, or process modification which results in new or increased discharges
of pollutants, or to operate such system or point source, or part thereof as so changed,
added to, or extended until plans and specifications therefor shall have been submitted to
the agencynew text begin ,new text end unless the agency deleted text begin shall have waived thedeleted text end new text begin waives new text end submission deleted text begin thereof to itdeleted text end new text begin of
the plans and specifications
new text end and a written permit deleted text begin therefor shall have beendeleted text end new text begin for the change,
addition, or extension is
new text end granted by the agency.

new text begin (b) If a person who discharges a pollutant into the waters of the state is required by
statute or rule to obtain a national pollutant discharge elimination system permit or a state
disposal system permit, the person may, prior to issuance of the permit, at the person's
own risk, act to change, add to, or extend an existing disposal system or point source, or
part thereof, unless the action taken:
new text end

new text begin (1) is prohibited by federal law or regulation;
new text end

new text begin (2) is by a municipality constructing a wastewater system with a design capacity of
200,000 gallons per day, or less;
new text end

new text begin (3) is subject to environmental review under chapter 116D, and prohibited from
commencing construction until that process is completed;
new text end

new text begin (4) is subject to a grant or loan agreement under chapter 446A;
new text end

new text begin (5) requires a construction storm water permit under rules of the agency; or
new text end

new text begin (6) requires a subsurface treatment system permit under rules of the agency.
new text end

new text begin The person is prohibited from operating the system or discharging pollutants into
the waters of the state until a written permit for the discharge is granted by the agency
and until plans and specifications for the disposal system have been approved, unless the
agency waives the submission of plans and specifications.
new text end

Sec. 3.

Minnesota Statutes 2010, section 116.03, is amended by adding a subdivision to
read:


new text begin Subd. 2b. new text end

new text begin Permitting efficiency. new text end

new text begin (a) It is the goal of the state that environmental and
resource management permits be issued or denied within 150 days of the submission of a
substantially completed permit application. The commissioner of the Pollution Control
Agency shall establish management systems designed to achieve the goal.
new text end

new text begin (b) The commissioner shall prepare semiannual permitting efficiency reports that
include statistics on meeting the goal in paragraph (a). The reports are due February 1 and
August 1 each year. For permit applications that have not met the goal, the report must
state the reasons for not meeting the goal, steps that will be taken to complete action on
the application, and the expected timeline. In stating the reasons for not meeting the
goal, the commissioner shall separately identify delays caused by the responsiveness of
the proposer, lack of staff, scientific or technical disagreements, or the level of public
engagement. The report must specify the number of days from initial submission of
the application to the day of determination that the application is complete. The report
for the final quarter of the fiscal year must aggregate the data for the year and assess
whether program or system changes are necessary to achieve the goal. The report must
be posted on the agency's Web site and submitted to the governor and the chairs and
ranking minority members of the house of representatives and senate committees having
jurisdiction over environment policy and finance.
new text end

new text begin (c) The commissioner shall allow electronic submission of environmental review
and permit documents to the agency.
new text end

new text begin (d) Beginning July 1, 2011, within 30 days of application for a permit subject to
paragraph (a), the commissioner of the Pollution Control Agency shall notify the project
proposer, in writing, of whether or not the permit application is complete enough for
processing. If the permit is incomplete, the commissioner must identify where deficiencies
exist and advise the applicant on how they can be remedied. A resubmittal of the
application begins a new 30-day review period. If the commissioner fails to notify the
project proposer of completeness within the 30-day period, the application is deemed to be
substantially complete and subject to the 150-day permitting review period in paragraph
(a) from the date it was submitted.
new text end

Sec. 4.

Minnesota Statutes 2010, section 116.07, subdivision 2, is amended to read:


Subd. 2.

Adoption of standards.

new text begin (a) new text end The Pollution Control Agency shall improve
air quality by promoting, in the most practicable way possible, the use of energy sources
and waste disposal methods which produce or emit the least air contaminants consistent
with the agency's overall goal of reducing all forms of pollution. The agency shall also
adopt standards of air quality, including maximum allowable standards of emission of air
contaminants from motor vehicles, recognizing that due to variable factors, no single
standard of purity of air is applicable to all areas of the state. In adopting standards the
Pollution Control Agency shall give due recognition to the fact that the quantity or
characteristics of air contaminants or the duration of their presence in the atmosphere,
which may cause air pollution in one area of the state, may cause less or not cause any air
pollution in another area of the state, and it shall take into consideration in this connection
such factors, including others which it may deem proper, as existing physical conditions,
zoning classifications, topography, prevailing wind directions and velocities, and the fact
that a standard of air quality which may be proper as to an essentially residential area of
the state, may not be proper as to a highly developed industrial area of the state. Such
standards of air quality shall be premised upon scientific knowledge of causes as well as
effects based on technically substantiated criteria and commonly accepted practices. No
local government unit shall set standards of air quality which are more stringent than
those set by the Pollution Control Agency.

new text begin (b) new text end The Pollution Control Agency shall promote solid waste disposal control
by encouraging the updating of collection systems, elimination of open dumps, and
improvements in incinerator practices. The agency shall also adopt standards for the
control of the collection, transportation, storage, processing, and disposal of solid waste
and sewage sludge for the prevention and abatement of water, air, and land pollution,
recognizing that due to variable factors, no single standard of control is applicable to
all areas of the state. In adopting standards, the Pollution Control Agency shall give
due recognition to the fact that elements of control which may be reasonable and proper
in densely populated areas of the state may be unreasonable and improper in sparsely
populated or remote areas of the state, and it shall take into consideration in this connection
such factors, including others which it may deem proper, as existing physical conditions,
topography, soils and geology, climate, transportation, and land use. Such standards of
control shall be premised on technical criteria and commonly accepted practices.

new text begin (c) new text end The Pollution Control Agency shall also adopt standards describing the
maximum levels of noise in terms of sound pressure level which may occur in the outdoor
atmosphere, recognizing that due to variable factors no single standard of sound pressure
is applicable to all areas of the state. Such standards shall give due consideration to
such factors as the intensity of noises, the types of noises, the frequency with which
noises recur, the time period for which noises continue, the times of day during which
noises occur, and such other factors as could affect the extent to which noises may be
injurious to human health or welfare, animal or plant life, or property, or could interfere
unreasonably with the enjoyment of life or property. In adopting standards, the Pollution
Control Agency shall give due recognition to the fact that the quantity or characteristics
of noise or the duration of its presence in the outdoor atmosphere, which may cause
noise pollution in one area of the state, may cause less or not cause any noise pollution
in another area of the state, and it shall take into consideration in this connection such
factors, including others which it may deem proper, as existing physical conditions,
zoning classifications, topography, meteorological conditions and the fact that a standard
which may be proper in an essentially residential area of the state, may not be proper as to
a highly developed industrial area of the state. Such noise standards shall be premised
upon scientific knowledge as well as effects based on technically substantiated criteria
and commonly accepted practices. No local governing unit shall set standards describing
the maximum levels of sound pressure which are more stringent than those set by the
Pollution Control Agency.

new text begin (d) new text end The Pollution Control Agency shall adopt standards for the identification of
hazardous waste and for the management, identification, labeling, classification, storage,
collection, transportation, processing, and disposal of hazardous waste, recognizing
that due to variable factors, a single standard of hazardous waste control may not be
applicable to all areas of the state. In adopting standards, the Pollution Control Agency
shall recognize that elements of control which may be reasonable and proper in densely
populated areas of the state may be unreasonable and improper in sparsely populated
or remote areas of the state. The agency shall consider existing physical conditions,
topography, soils, and geology, climate, transportation and land use. Standards of
hazardous waste control shall be premised on technical knowledge, and commonly
accepted practices. Hazardous waste generator licenses may be issued for a term not to
exceed five years. No local government unit shall set standards of hazardous waste control
which are in conflict or inconsistent with those set by the Pollution Control Agency.

new text begin (e) new text end A person who generates less than 100 kilograms of hazardous waste per month is
exempt from the following agency hazardous waste rules:

(1) rules relating to transportation, manifesting, storage, and labeling for
photographic fixer and x-ray negative wastes that are hazardous solely because of silver
content; and

(2) any rule requiring the generator to send to the agency or commissioner a copy
of each manifest for the transportation of hazardous waste for off-site treatment, storage,
or disposal, except that counties within the metropolitan area may require generators to
provide manifests.

Nothing in this paragraph exempts the generator from the agency's rules relating to on-site
accumulation or outdoor storage. A political subdivision or other local unit of government
may not adopt management requirements that are more restrictive than this paragraph.

new text begin (f) In any rulemaking proceeding under chapter 14 to adopt standards for air quality,
solid waste, or hazardous waste under this chapter, or standards for water quality under
chapter 115, that are more stringent than any similar federal standard adopted under
the Clean Air Act, United States Code, title 42, section 7412(b)(2); the Clean Water
Act, United States Code, title 33, sections 1312(a) and 1313(c)(4); and the Resource
Conservation and Recovery Act, United States Code, title 42, section 6921(b)(1), the
statement of need and reasonableness must include documentation that the federal
standard does not provide adequate protection for public health and the environment and
a comparison of the proposed standard with standards in border states and states within
Environmental Protection Agency Region 5.
new text end

new text begin APPLICATION. new text end

new text begin This section applies to proceedings in which the notice under
section 14.14, subdivision 1a, or 14.22, is made on or after the effective date.
new text end

Sec. 5.

Minnesota Statutes 2010, section 116D.04, subdivision 2a, is amended to read:


Subd. 2a.

When prepared.

Where there is potential for significant environmental
effects resulting from any major governmental action, the action shall be preceded by a
detailed environmental impact statement prepared by the responsible governmental unit.
The environmental impact statement shall be an analytical rather than an encyclopedic
document which describes the proposed action in detail, analyzes its significant
environmental impacts, discusses appropriate alternatives to the proposed action and
their impacts, and explores methods by which adverse environmental impacts of an
action could be mitigated. The environmental impact statement shall also analyze those
economic, employment and sociological effects that cannot be avoided should the action
be implemented. To ensure its use in the decision-making process, the environmental
impact statement shall be prepared as early as practical in the formulation of an action.
No mandatory environmental impact statement may be required for an ethanol plant,
as defined in section 41A.09, subdivision 2a, paragraph (b), that produces less than
125,000,000 gallons of ethanol annually and is located outside of the seven-county
metropolitan area.

(a) The board shall by rule establish categories of actions for which environmental
impact statements and for which environmental assessment worksheets shall be prepared
as well as categories of actions for which no environmental review is required under
this section.

(b) The responsible governmental unit shall promptly publish notice of the
completion of an environmental assessment worksheet in a manner to be determined by
the board and shall provide copies of the environmental assessment worksheet to the board
and its member agencies. Comments on the need for an environmental impact statement
may be submitted to the responsible governmental unit during a 30-day period following
publication of the notice that an environmental assessment worksheet has been completed.
The responsible governmental unit's decision on the need for an environmental impact
statement shall be based on the environmental assessment worksheet and the comments
received during the comment period, and shall be made within 15 days after the close of
the comment period. The board's chair may extend the 15-day period by not more than 15
additional days upon the request of the responsible governmental unit.

(c) An environmental assessment worksheet shall also be prepared for a proposed
action whenever material evidence accompanying a petition by not less than 25
individuals, submitted before the proposed project has received final approval by the
appropriate governmental units, demonstrates that, because of the nature or location of a
proposed action, there may be potential for significant environmental effects. Petitions
requesting the preparation of an environmental assessment worksheet shall be submitted to
the board. The chair of the board shall determine the appropriate responsible governmental
unit and forward the petition to it. A decision on the need for an environmental assessment
worksheet shall be made by the responsible governmental unit within 15 days after the
petition is received by the responsible governmental unit. The board's chair may extend
the 15-day period by not more than 15 additional days upon request of the responsible
governmental unit.

(d) Except in an environmentally sensitive location where Minnesota Rules, part
4410.4300, subpart 29, item B, applies, the proposed action is exempt from environmental
review under this chapter and rules of the board, if:

(1) the proposed action is:

(i) an animal feedlot facility with a capacity of less than 1,000 animal units; or

(ii) an expansion of an existing animal feedlot facility with a total cumulative
capacity of less than 1,000 animal units;

(2) the application for the animal feedlot facility includes a written commitment by
the proposer to design, construct, and operate the facility in full compliance with Pollution
Control Agency feedlot rules; and

(3) the county board holds a public meeting for citizen input at least ten business
days prior to the Pollution Control Agency or county issuing a feedlot permit for the
animal feedlot facility unless another public meeting for citizen input has been held with
regard to the feedlot facility to be permitted. The exemption in this paragraph is in
addition to other exemptions provided under other law and rules of the board.

(e) The board may, prior to final approval of a proposed project, require preparation
of an environmental assessment worksheet by a responsible governmental unit selected
by the board for any action where environmental review under this section has not been
specifically provided for by rule or otherwise initiated.

(f) An early and open process shall be utilized to limit the scope of the environmental
impact statement to a discussion of those impacts, which, because of the nature or location
of the project, have the potential for significant environmental effects. The same process
shall be utilized to determine the form, content and level of detail of the statement as well
as the alternatives which are appropriate for consideration in the statement. In addition,
the permits which will be required for the proposed action shall be identified during the
scoping process. Further, the process shall identify those permits for which information
will be developed concurrently with the environmental impact statement. The board
shall provide in its rules for the expeditious completion of the scoping process. The
determinations reached in the process shall be incorporated into the order requiring the
preparation of an environmental impact statement.

(g) The responsible governmental unit shall, to the extent practicable, avoid
duplication and ensure coordination between state and federal environmental review
and between environmental review and environmental permitting. Whenever practical,
information needed by a governmental unit for making final decisions on permits or
other actions required for a proposed project shall be developed in conjunction with the
preparation of an environmental impact statement.

(h) An environmental impact statement shall be prepared and its adequacy
determined within 280 days after notice of its preparation unless the time is extended by
consent of the parties or by the governor for good cause. The responsible governmental
unit shall determine the adequacy of an environmental impact statement, unless within 60
days after notice is published that an environmental impact statement will be prepared,
the board chooses to determine the adequacy of an environmental impact statement. If an
environmental impact statement is found to be inadequate, the responsible governmental
unit shall have 60 days to prepare an adequate environmental impact statement.

new text begin (i) The proposer of a specific action may include in the information submitted to the
responsible governmental unit a preliminary draft environmental impact statement under
this section on that action for review, modification, and determination of completeness and
adequacy by the responsible governmental unit. A preliminary draft environmental impact
statement prepared by the project proposer and submitted to the responsible governmental
unit shall identify or include as an appendix all studies and other sources of information
used to substantiate the analysis contained in the preliminary draft environmental impact
statement. The responsible governmental unit shall require additional studies, if needed,
and obtain from the project proposer all additional studies and information necessary for
the responsible governmental unit to perform its responsibility to review, modify, and
determine the completeness and adequacy of the environmental impact statement.
new text end

Sec. 6.

Minnesota Statutes 2010, section 116D.04, subdivision 3a, is amended to read:


Subd. 3a.

Final decisions.

Within deleted text begin 90deleted text end new text begin 30 new text end days after final approval of an
environmental impact statement, final decisions shall be made by the appropriate
governmental units on those permits which were identified as required and for which
information was developed concurrently with the preparation of the environmental impact
statement. Provided, however, that the deleted text begin 90-daydeleted text end new text begin 30-daynew text end period may be extended where a
longer period is new text begin permitted by section 15.99 ornew text end required by federal law or state statute or is
consented to by the permit applicant. The permit decision shall include the reasons for
the decision, including any conditions under which the permit is issued, together with a
final order granting or denying the permit.

new text begin APPLICATION. new text end

new text begin This section applies to matters in which final approval of an
environmental impact statement is made on or after the effective date.
new text end

Sec. 7.

Minnesota Statutes 2010, section 116D.04, subdivision 10, is amended to read:


Subd. 10.

Review.

deleted text begin Decisionsdeleted text end new text begin A person aggrieved by a final decision new text end on the need for
an environmental assessment worksheet, the need for an environmental impact statement
deleted text begin anddeleted text end new text begin , or new text end the adequacy of an environmental impact statement deleted text begin may be reviewed by a
declaratory judgment action in the district court of the county wherein the proposed action,
or any part thereof, would be undertaken
deleted text end new text begin is entitled to judicial review of the decision
under sections 14.63 to 14.68. A petition for a writ of certiorari by an aggrieved person
for judicial review under sections 14.63 to 14.68 must be filed with the Court of Appeals
and served on the responsible governmental unit not more than 30 days after the party
receives the final decision and order of the responsible governmental unit. Proceedings for
review under this section must be instituted by serving a petition for a writ of certiorari
personally or by certified mail upon the responsible governmental unit and by promptly
filing the proof of service in the Office of the Clerk of the Appellate Courts and the
matter will proceed in the manner provided by the Rules of Civil Appellate Procedure.
A copy of the petition must be provided to the attorney general at the time of service.
Copies of the writ must be served, personally or by certified mail, upon the responsible
governmental unit and the project proposer. The filing of the writ of certiorari does not
stay the enforcement of any other governmental action, provided that the responsible
governmental unit may stay enforcement or the Court of Appeals may order a stay upon
terms it deems proper
new text end . deleted text begin Judicial review under this section shall be initiated within 30
days after the governmental unit makes the decision, and
deleted text end A bond may be required under
section 562.02 unless at the time of hearing on the application for the bond the deleted text begin plaintiffdeleted text end
new text begin petitioner-relator new text end has shown that the claim deleted text begin has sufficient possibility of successdeleted text end new text begin is likely
to succeed
new text end on the merits deleted text begin to sustain the burden required for the issuance of a temporary
restraining order. Nothing in this section shall be construed to alter the requirements for a
temporary restraining order or a preliminary injunction pursuant to the Minnesota Rules of
Civil Procedure for district courts
deleted text end . The board may initiate judicial review of decisions
referred to herein and new text begin the board or a project proposer new text end may intervene as of right in any
proceeding brought under this subdivision.

new text begin APPLICATION. new text end

new text begin This section applies to matters in which the final decision that is
subject to judicial review is made on or after the effective date.
new text end

Sec. 8.

Minnesota Statutes 2010, section 116D.045, subdivision 1, is amended to read:


Subdivision 1.

Assessment.

The board shall by rule adopt procedures to assess
the proposer of a specific action for reasonable costs of preparingnew text begin , reviewing,new text end and
distributing deleted text begin andeleted text end new text begin the new text end environmental impact statement deleted text begin on that action required pursuant to
section 116D.04
deleted text end . deleted text begin Suchdeleted text end new text begin Thenew text end costs shall be determined by the responsible governmental
unit pursuant to the rules promulgated by the board.

Sec. 9.

Minnesota Statutes 2010, section 116D.045, subdivision 3, is amended to read:


Subd. 3.

Use of assessment.

new text begin As necessary, new text end the responsible governmental unit shall
assess the project proposer for reasonable costsnew text begin that the responsible governmental unit
incurs
new text end in preparingnew text begin , reviewing,new text end and distributing the environmental impact statement and
the proposer shall pay the assessed cost to the responsible governmental unit. Money
received under this subdivision by a responsible governmental unit may be retained by the
unit for the same purposes. Money received by a state agency must be credited to a special
account and is appropriated to the agency to cover the assessed costs incurred.

Sec. 10. new text begin RULE AMENDMENT.
new text end

new text begin The commissioner of the Pollution Control Agency, the commissioner of natural
resources, and the Environmental Quality Board, must amend rules necessary to conform
to this act. The commissioners and the board may use the good cause exemption under
Minnesota Statutes, section 14.388, subdivision 1, clause (3), and Minnesota Statutes,
section 14.386, does not apply, except as provided in Minnesota Statutes, section 14.388.
new text end

Sec. 11. new text begin EFFECTIVE DATE.
new text end

new text begin This act is effective the day following final enactment.
new text end